Risk practice
Definition
The risk practice describes how a PRINCE2 project deals with uncertainty. Risks can have a negative effect (threats) or a positive one (opportunities); both are handled by the same procedure. The practice provides a recurring cycle: identify risks, assess them by probability and impact, plan suitable responses, implement them and report on their status. How this cycle works in the individual project is recorded in the risk management approach; the individual risks are kept in a register. The risk appetite of the commissioning organization determines which tolerances for risk the project board grants the project.
Equivalents in other frameworks
Concept Systematic handling of uncertainty in a project · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Risk management | closely related | Tailored to the individual project and linked to the business case, plans and tolerances. |
| general | Risk management | closely related | Tailored to the individual project and linked to the business case, plans and tolerances. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Other terms
Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.
- Risk theme
- deprecated
Classification
- this term
- Risk practice
- Topic area
- Risks and opportunities
Distinction
General risk management can relate to an entire organization. The risk practice is tailored to the individual project and connected to the other practices: risks feed into the business case, and their assessment influences plans and tolerances. Problems that have already occurred do not belong here but to the issues practice.
In practice
A hospital is moving its laboratories into a new building. In a workshop, the team names, among others, the risk that sensitive measuring instruments lose their calibration in transit. Probability is rated medium, impact high. As a response, it is agreed to schedule a service technician from the manufacturer on site for the first few days. The opportunity to retire older instruments at the same time is recorded as well.
Frequently asked questions
Does PRINCE2 treat opportunities in the same way as threats?
Yes. Both count as risks and are identified, assessed and controlled in the same way; only the responses differ, because opportunities are to be exploited rather than warded off.
Who decides how a risk is handled?
A responsible person is named for each risk. If a risk exceeds the limits set by the project board, the board decides.
Source and context
- Reference
- PRINCE2 7, Praktik Risiko
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Risk practice. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-practice/
Hain, D. (n.d.): Risk practice. PMDecoder, entry on PRINCE2 7, Praktik Risiko. https://pmdecoder.com/en/glossary/risk-practice/ (retrieved 24 November 2026)
@misc{riskpractice,
author = {Hain, Dennis},
title = {Risk practice},
note = {PMDecoder, PRINCE2 7, Praktik Risiko},
url = {https://pmdecoder.com/en/glossary/risk-practice/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-practice/"> <p>PRINCE2 7 practice for identifying, assessing and controlling uncertainties that threaten or favour the project’s objectives.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-practice/">Risk practice</a>, PMDecoder, PRINCE2 7, Praktik Risiko</footer> </blockquote>
Found a mistake? Let us know, we check every report.