Business Case

Definition

In PRINCE2, the business case is the management product that records a project’s business justification. It describes the reasons for the undertaking, the options considered including doing nothing, the expected benefits and possible dis-benefits, costs, timescale, major risks and the investment appraisal. An outline version is created at the start as part of the project brief; during initiation it is developed into a detailed business case that becomes part of the project initiation documentation. After that, it is updated at each stage boundary and in exceptions, and the project board uses it as the basis for deciding whether to continue.

Equivalents in other frameworks

Concept Economic justification of an initiative · two frameworks reviewed

Equivalents of Business Case in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Business caseequivalent—
PMI / PMBOKBusiness caseequivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Business Case
Topic area
Initiating

Distinction

ISO 21506 and PMI also understand a business case as the economic justification of an undertaking. What is characteristic of PRINCE2 is that the business case is not only checked before the start but kept up to date throughout the project. It is part of the project initiation documentation, whereas the business case practice describes how it is handled.

In practice

An insurer wants to automate its claims handling. The outline business case compares three options: change nothing, customize standard software or develop in-house. During initiation, the costs of the standard software are established more precisely and the savings per claim are evidenced. After the second stage licence costs rise; the business case is adjusted and remains just positive, and the project board authorizes the next stage.

Frequently asked questions

Who is responsible for the business case?

The executive. The executive ensures that the project remains justified. The project manager usually prepares and updates the business case on the executive’s behalf.

What about projects that are required by law?

They need a business case too. It then compares ways of meeting the obligation and justifies why the chosen solution is the most sensible one.

Source and context

Reference
PRINCE2 7, Praktik Business Case
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Business Case. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/business-case-prince2/

Short form

Hain, D. (n.d.): Business Case. PMDecoder, entry on PRINCE2 7, Praktik Business Case. https://pmdecoder.com/en/glossary/business-case-prince2/ (retrieved 24 November 2026)

BibTeX
@misc{businesscaseprince2,
  author  = {Hain, Dennis},
  title   = {Business Case},
  note    = {PMDecoder, PRINCE2 7, Praktik Business Case},
  url     = {https://pmdecoder.com/en/glossary/business-case-prince2/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/business-case-prince2/">
  <p>PRINCE2 management product justifying why a project is worthwhile, kept up to date throughout the project’s life.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/business-case-prince2/">Business Case</a>, PMDecoder, PRINCE2 7, Praktik Business Case</footer>
</blockquote>

Found a mistake? Let us know, we check every report.