Cost variance
abbr. CV
Definition
Cost variance indicates how economically a project or programme has worked so far: it shows whether the work done has cost more or less than was budgeted for it. In earned value management it is calculated as earned value minus actual cost. A negative value means that more was spent on the work than intended, a positive value that it was done more cheaply. It is often also given as a percentage of earned value to put it into perspective.
Equivalents in other frameworks
Concept Difference between earned value and actual cost · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Cost variance | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Cost variance
- Topic area
- Monitoring and control
Distinction
A simple comparison of planned and actual costs at a given date mixes up cost and schedule variances: a project that has done less has usually also spent less. Cost variance based on earned value avoids this error because it relates costs to the work actually performed. Variance at completion, by contrast, compares the total budget with the forecast total cost.
In practice
A machine builder is constructing a special-purpose plant. At the end of the month, assemblies with a budget of 420,000 euros are complete, but they have cost 465,000 euros. The cost variance is minus 45,000 euros, or about minus eleven per cent. Analysis by work package shows that almost all of the variance comes from the control engineering, where expensive rework was needed. The other assemblies are within budget.
Frequently asked questions
Is a positive cost variance always good?
Usually, yes. However, it can also point to overly generous estimates or to costs that have not yet been booked, which should be checked.
When is action needed?
When the variance exceeds agreed tolerances or keeps growing over several reporting periods.
Source and context
- Reference
- ISO 21506:2024, 3.17
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Cost variance. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-variance/
Hain, D. (n.d.): Cost variance. PMDecoder, entry on ISO 21506:2024, 3.17. https://pmdecoder.com/en/glossary/cost-variance/ (retrieved 24 November 2026)
@misc{costvariance,
author = {Hain, Dennis},
title = {Cost variance},
note = {PMDecoder, ISO 21506:2024, 3.17},
url = {https://pmdecoder.com/en/glossary/cost-variance/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/cost-variance/"> <p>Difference between the value of the work performed and the actual cost incurred for it; a negative value means more expensive than planned.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-variance/">Cost variance</a>, PMDecoder, ISO 21506:2024, 3.17</footer> </blockquote>
Found a mistake? Let us know, we check every report.