Risk acceptance

Definition

In PMI terms, risk acceptance is one of the strategies for responding to a risk. The project acknowledges the risk but does not change its plan to influence it. The strategy is appropriate when other responses are uneconomic or impossible, or when the risk is so small that further effort is not worthwhile. PMI distinguishes an active form, in which reserves of time or money or a plan for the event are kept ready, from a passive form, in which the risk is simply reviewed periodically. The strategy can be applied to threats as well as to opportunities.

Equivalents in other frameworks

Concept Consciously accepting a risk · three frameworks reviewed

Equivalents of Risk acceptance in other frameworks
FrameworkTerm thereRelationNote
generalRisk acceptanceequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Risk response
this term
Risk acceptance

Distinction

In substance the term corresponds to the cross-framework concept of risk acceptance. Unlike risk avoidance or risk mitigation, risk acceptance does not act on the cause, probability or impact. It should not be confused with risk appetite: that describes how much uncertainty an organization is generally willing to accept, whereas risk acceptance is a decision about an individual risk.

In practice

An events project realizes that a speaker could cancel at short notice. Securing a second speaker would be expensive. The team opts for active risk acceptance: it draws up a short list of possible replacement topics that in-house staff could present and monitors the situation up to the date.

Frequently asked questions

Is risk acceptance the same as doing nothing?

No. The decision is taken deliberately and documented. With active acceptance, reserves or a plan for the event are kept ready; even with passive acceptance the risk remains under review.

When does risk acceptance make sense?

Mainly for risks of low significance, or when any other response would cost more than the potential damage. The result should lie within the organization's risk thresholds.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk acceptance. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-acceptance-pmi/

Short form

Risk acceptance (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-acceptance-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{riskacceptancepmi,
  title   = {Risk acceptance},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-acceptance-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-acceptance-pmi/">
  <p>Response strategy of consciously tolerating a risk and taking no advance measures against or in favor of its occurrence.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-acceptance-pmi/">Risk acceptance</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.