Cost performance index

abbr. CPI

Definition

The cost performance index describes the cost efficiency of a project as the ratio of earned value to actual cost. A value of 1.0 means that every euro spent has produced exactly one euro of planned work; 0.8 means only 80 cents. As a ratio, it allows projects of different sizes to be compared. It is also the basis of a widely used forecast: the total budget divided by the index gives the expected total cost if the efficiency achieved so far continues.

Equivalents in other frameworks

Concept Cost efficiency of work performed · three frameworks reviewed

Equivalents of Cost performance index in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKCost performance indexequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Cost performance index

Distinction

Cost variance gives the difference in euros, the index the ratio. The schedule performance index measures progress against the plan, not costs. Analyses of many large projects suggest that a cost index well below one rarely improves fundamentally after the first third of a project.

In practice

A plant manufacturer compares four ongoing projects of different sizes. The cost performance index is 1.02, 0.97, 0.95 and 0.78. Although the fourth project is the smallest, it receives the most attention: with a budget of 800,000 euros, it would cost around 1.03 million euros if its efficiency stayed the same. A review shows that a subcontractor is billing considerably more hours than calculated.

Frequently asked questions

How is the cost performance index calculated?

As earned value divided by actual cost, each cumulative up to the reporting date.

What is a good cost performance index?

Values around 1.0 are considered on plan. Organizations often set thresholds, for example to look more closely from 0.95 and to escalate from 0.9.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Cost performance index. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-performance-index/

Short form

Hain, D. (n.d.): Cost performance index. PMDecoder. https://pmdecoder.com/en/glossary/cost-performance-index/ (retrieved 24 November 2026)

BibTeX
@misc{costperformanceindex,
  author  = {Hain, Dennis},
  title   = {Cost performance index},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/cost-performance-index/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/cost-performance-index/">
  <p>Ratio of earned value to actual cost; values below one mean that the project is working at higher cost than planned</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-performance-index/">Cost performance index</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.