Cost planning

also: Budget planning

Definition

Cost planning builds on the cost estimate and assigns the expected costs to work packages, cost types and time periods. The result is a time-phased cost plan showing when which funds are needed. Once approved, it serves as the baseline against which actual costs are compared, and as the basis for the organization's liquidity planning.

Equivalents in other frameworks

Concept Setting costs by time and project component · three frameworks reviewed

Equivalents of Cost planning in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKCost management planpartially overlappingdenotes the plan containing the rules for estimating, budgeting and controlling costs
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Other terms

Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.

Cost plan
related, not equivalent
Budget planning
synonym

Classification

this term
Cost planning

Distinction

Cost estimation asks how much something will cost; cost planning asks when and where these costs will be incurred and how much will be released for them. Cost management additionally covers monitoring and control. Financial planning looks at cash flows, cost planning at the consumption of value; the two can diverge in time, for example with advance payments.

In practice

A research consortium plans a three-year project with four partners. Cost planning distributes the estimated 2.4 million euros across partners, work packages and quarters. This reveals that expensive laboratory equipment has to be bought in the first half-year, whereas the grant money flows evenly over the term. The consortium therefore applies for an adjusted drawdown schedule before a small partner runs short of liquidity.

Frequently asked questions

What belongs in a cost plan?

Costs by work package and cost type, their distribution over time, reserves and the assumptions on which the values are based.

How are the cost plan and the S-curve related?

The plan's costs accumulated over time form the S-curve, which is compared with actual costs as the project proceeds.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Cost planning. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-planning/

Short form

Hain, D. (n.d.): Cost planning. PMDecoder. https://pmdecoder.com/en/glossary/cost-planning/ (retrieved 24 November 2026)

BibTeX
@misc{costplanning,
  author  = {Hain, Dennis},
  title   = {Cost planning},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/cost-planning/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/cost-planning/">
  <p>Specifying which costs may be incurred when and for which parts of a project, as the basis for budget and cost control</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-planning/">Cost planning</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.