Baseline
Definition
At PMI, a baseline is the approved state of a work product, usually a plan, against which actual performance is measured. It may be adjusted only through formal change control. In the predictive approach, PMI mainly distinguishes the scope baseline, consisting of the scope statement, the work breakdown structure and its dictionary, the schedule baseline and the cost baseline. Together they form the performance measurement baseline, against which the earned value evaluation is calculated, for example. A baseline records a state; the current plan may deviate from it.
Equivalents in other frameworks
Concept Approved reference version of a plan · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Baseline | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Baseline
- Topic area
- Monitoring and control
Distinction
“Basisplan” (baseline) according to ISO 21506, which represents the concept in the glossary, is equivalent. A baseline is not the current plan but the approved reference point. When it is changed, the old version should be kept so that variances and changes remain traceable. Adaptive approaches often work with lighter reference points, such as a release goal.
In practice
After the project management plan has been approved, the project manager saves the schedule as a baseline. Three months later the forecast acceptance date is two weeks behind the baseline date. The report shows both dates side by side. Only when the steering committee approves a change request is a new baseline set and the old one archived.
Frequently asked questions
May a baseline be changed?
Yes, but only through formal change control, that is with an approved change request. Silently overwriting it would conceal variances and destroy the value of reporting.
Which baselines does PMI use?
Common ones are the scope, schedule and cost baselines, which together form the performance measurement baseline. In principle, any approved work product can serve as a baseline, such as a set of requirements.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Baseline. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/baseline-pmi/
Baseline (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/baseline-pmi/ (retrieved 24 November 2026)
@misc{baselinepmi,
title = {Baseline},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/baseline-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/baseline-pmi/"> <p>Frozen, approved version of a plan or work product that actual progress is measured against and that only an authorized change may alter.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/baseline-pmi/">Baseline</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.