Lessons learned
Definition
Lessons learned are insights from a project that are recorded so that the same project or later undertakings can benefit from them. They describe what worked well and should be kept, as well as mistakes, surprises and detours that can be avoided in future. In PMI practice they are collected throughout the project rather than only at the end, and kept in a register or a similar store. After the project closes, they become part of the organization’s knowledge base and are thus available to other projects. They are most valuable when they link cause, effect and a specific recommendation.
Equivalents in other frameworks
Concept Captured lessons from projects · seven frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Lessons learned | equivalent | — |
| PRINCE2 | Lessons Report | closely related | Report that evaluates selected lessons and passes them on to the organization. |
| PRINCE2 | Learn from experience principle | partially overlapping | Principle of using lessons at the start, throughout and at the end, not the lessons themselves. |
| PRINCE2 | Lessons Log | partially overlapping | Log in which lessons are collected during the project. |
| PRINCE2 | End Project Report | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| PM² | Project-End Report | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| Scrum | Sprint Retrospective | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Lessons learned
- Topic area
- Closing
Distinction
Lessons learned under ISO 21506 refer to the same thing. The Scrum Sprint Retrospective also draws on experience, but aims at how the team itself works in the next Sprint. In PRINCE2, lessons are gathered in the Lessons Log and passed on in the Lessons Report; the Learn from experience principle calls for them to be used continually. The PM² Project-End Report contains lessons but also reports on performance and outcome. Knowledge management is the wider framework in which an organization makes such insights easy to find.
In practice
An energy utility is building four substations over three years. At the first one, commissioning is delayed by two months because the grid operator allocates its inspection dates with a long lead time. The team records this as a lesson learned while the project is still running, together with the recommendation to apply for inspection dates as soon as construction starts. The managers of the following substations add this step to their schedules, and the project office adds the point to its checklist for substation projects.
Frequently asked questions
When should lessons learned be collected?
Not only at the end of the project. Recording insights continuously, or at least at the end of each phase, keeps them accurate and allows them to be used within the same project. The closing review then brings them together.
What makes lessons learned effective?
They need to be specific, contain a recommendation and be stored where future projects will find them. A collection that nobody reads changes nothing. Insights only take effect once they are built into the organization’s templates, checklists or rules.
How do lessons learned differ from a retrospective?
A retrospective takes place at regular intervals in agile teams and mainly improves collaboration within the team. Lessons learned are aimed more at the organization and are documented so that other projects can benefit as well.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Lessons learned. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/lessons-learned/
Lessons learned (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/lessons-learned/ (retrieved 24 November 2026)
@misc{lessonslearned,
title = {Lessons learned},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/lessons-learned/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/lessons-learned/"> <p>Documented insights from the course of a project for future undertakings.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/lessons-learned/">Lessons learned</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.