Risk
Definition
A risk exists when it is still open whether an event will occur and it would have consequences for a project, programme or portfolio if it did. ISO 21506 uses the term neutrally: the consequences can be negative, in which case it is a threat, or positive, in which case it is an opportunity. A risk can also consist of several related events, such as a chain of delivery delays. Risks are identified, assessed by probability and impact, and given responses.
Equivalents in other frameworks
Concept Risk in a project · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Risk | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Risk
- Topic area
- Risks and opportunities
Distinction
In everyday language, risk usually means only the negative side. An issue has already occurred and is no longer a risk. ISO 31000 describes risk more generally as the effect of uncertainty on objectives, whereas ISO 21506 focuses on the uncertain event itself.
In practice
A publisher plans to launch a new learning platform at the start of the school year. The risk register contains, among others, two entries: the interface to the school administration software could be delayed, a threat with high impact; and a federal state could launch a funding programme for digital learning materials, an opportunity that would significantly increase demand. For the threat, a second development route is prepared; for the opportunity, server capacity that can be expanded at short notice.
Frequently asked questions
Can a risk also be positive?
Yes. If risk is understood as a deviation from objectives, it can go either way. Possible positive deviations are often called opportunities, for example a component that becomes available earlier or a lower purchase price.
What is the difference between a risk and an issue?
A risk is uncertain and lies in the future: it may or may not occur. An issue has already occurred and has to be dealt with. A risk that materializes therefore becomes an issue.
How is a risk assessed?
The usual approach is to estimate probability and impact, either in levels such as low, medium and high or in figures. The assessment shows which risks are dealt with first and need responses.
Source and context
- Reference
- ISO 21506:2024, 3.76
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Risk. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk/
Hain, D. (n.d.): Risk. PMDecoder, entry on ISO 21506:2024, 3.76. https://pmdecoder.com/en/glossary/risk/ (retrieved 24 November 2026)
@misc{risk,
author = {Hain, Dennis},
title = {Risk},
note = {PMDecoder, ISO 21506:2024, 3.76},
url = {https://pmdecoder.com/en/glossary/risk/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk/"> <p>Possible event that is still uncertain, possibly made up of several events, and that could benefit or harm an undertaking.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk/">Risk</a>, PMDecoder, ISO 21506:2024, 3.76</footer> </blockquote>
Found a mistake? Let us know, we check every report.