Project-End Report

Definition

In PM², the Project-End Report is produced after the Project-End Review Meeting and brings together the project's experience. It describes good practices, lessons learned, difficulties encountered and how they were resolved, and it assesses the effectiveness of the project as well as the management of costs, schedule, scope, quality, risks, issues, changes, communication, staffing and stakeholders. Recommendations for the period after the project, for example on maintenance, enhancements or follow-up projects, are also included. The Project Manager writes it with support from the core team and quality assurance; it is meant to serve future projects as a knowledge base.

Equivalents in other frameworks

Concept Captured lessons from projects · seven frameworks reviewed

Equivalents of Project-End Report in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Lessons learnedpartially overlappingcontains lessons learned, but also reports on the performance and outcome of the project
PMI / PMBOKLessons learnedpartially overlappingcontains lessons learned, but also reports on the performance and outcome of the project
PRINCE2Learn from experience principlepartially overlappingPrinciple of using lessons at the start, throughout and at the end, not the lessons themselves.
PRINCE2Lessons Logpartially overlappingLog in which lessons are collected during the project.
PRINCE2Lessons Reportpartially overlappingcontains lessons learned, but also reports on the performance and outcome of the project
PRINCE2End Project Reportpartially overlappingMainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report.
ScrumSprint Retrospectivepartially overlappingcontinually improves the way the team works instead of documenting lessons for other initiatives

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project-End Report
Topic area
Closing

Distinction

Lessons learned are one component; the report is broader and also assesses project performance. The Project Progress Report, by contrast, describes the status during the project, whereas the Project-End Report looks back on the project as a whole.

In practice

The Project-End Report for a portal for election volunteers records that the budget was kept but the deadline was missed by four weeks because the interface to the population register became available later than planned. It recommends clarifying external interfaces bindingly as early as initiation in future and proposes an extension for postal voting volunteers as a follow-up project.

Frequently asked questions

Who contributes to the Project-End Report?

The Project Manager writes it but should involve the relevant stakeholders so that the assessment is complete and balanced.

Is the report also prepared for cancelled projects?

Yes. It is precisely then that it pays to record why the project was not continued and what future projects can learn from it.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 8.2
Edition
PM² Guide 3.1
Cite this entry
APA

Project-End Report. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-end-report/

Short form

Project-End Report (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 8.2. https://pmdecoder.com/en/glossary/project-end-report/ (retrieved 24 November 2026)

BibTeX
@misc{projectendreport,
  title   = {Project-End Report},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 8.2},
  url     = {https://pmdecoder.com/en/glossary/project-end-report/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-end-report/">
  <p>PM² artefact at the end of a project recording performance, good practices, difficulties and recommendations as a knowledge base</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-end-report/">Project-End Report</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 8.2</footer>
</blockquote>

Found a mistake? Let us know, we check every report.