Project-End Report
Definition
In PM², the Project-End Report is produced after the Project-End Review Meeting and brings together the project's experience. It describes good practices, lessons learned, difficulties encountered and how they were resolved, and it assesses the effectiveness of the project as well as the management of costs, schedule, scope, quality, risks, issues, changes, communication, staffing and stakeholders. Recommendations for the period after the project, for example on maintenance, enhancements or follow-up projects, are also included. The Project Manager writes it with support from the core team and quality assurance; it is meant to serve future projects as a knowledge base.
Equivalents in other frameworks
Concept Captured lessons from projects · seven frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Lessons learned | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PMI / PMBOK | Lessons learned | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PRINCE2 | Learn from experience principle | partially overlapping | Principle of using lessons at the start, throughout and at the end, not the lessons themselves. |
| PRINCE2 | Lessons Log | partially overlapping | Log in which lessons are collected during the project. |
| PRINCE2 | Lessons Report | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PRINCE2 | End Project Report | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| Scrum | Sprint Retrospective | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project-End Report
- Topic area
- Closing
Distinction
Lessons learned are one component; the report is broader and also assesses project performance. The Project Progress Report, by contrast, describes the status during the project, whereas the Project-End Report looks back on the project as a whole.
In practice
The Project-End Report for a portal for election volunteers records that the budget was kept but the deadline was missed by four weeks because the interface to the population register became available later than planned. It recommends clarifying external interfaces bindingly as early as initiation in future and proposes an extension for postal voting volunteers as a follow-up project.
Frequently asked questions
Who contributes to the Project-End Report?
The Project Manager writes it but should involve the relevant stakeholders so that the assessment is complete and balanced.
Is the report also prepared for cancelled projects?
Yes. It is precisely then that it pays to record why the project was not continued and what future projects can learn from it.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 8.2
- Edition
- PM² Guide 3.1
Cite this entry
Project-End Report. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-end-report/
Project-End Report (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 8.2. https://pmdecoder.com/en/glossary/project-end-report/ (retrieved 24 November 2026)
@misc{projectendreport,
title = {Project-End Report},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 8.2},
url = {https://pmdecoder.com/en/glossary/project-end-report/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-end-report/"> <p>PM² artefact at the end of a project recording performance, good practices, difficulties and recommendations as a knowledge base</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-end-report/">Project-End Report</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 8.2</footer> </blockquote>
Found a mistake? Let us know, we check every report.