Late start date
Definition
The late start date, LS for short, is the latest date on which an activity not yet started may begin without moving the project end or breaching a schedule constraint. It is calculated in the backward pass by subtracting the activity's duration from its late finish date. The late start date is thus a limit: if the activity starts later and its duration stays the same, the project end inevitably moves. For activities on the critical path, the early start date and the late start date coincide.
Equivalents in other frameworks
Concept Latest allowable start of an activity · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Late start date | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Late start date
- Topic area
- Network planning
Distinction
The late start date corresponds to the German spätester Anfangszeitpunkt in network planning. The early start date is the earliest possible start; as with the finish dates, the difference between the two is the total float. The start actually scheduled may lie anywhere between the two and is often set according to resource availability.
In practice
For a website redesign, the schedule calculation shows that writing the texts for the product section can start on 2 April at the earliest and 23 April at the latest. Because the editor is first working on a campaign in April, the project manager sets the start for 16 April. This still leaves a week of reserve up to the late start date.
Frequently asked questions
How are the late start date and late finish date related?
The late start date is the late finish date minus the activity's duration. If the estimated duration changes, the late start date moves accordingly.
How is the late start date used in practice?
As an early warning threshold. If an activity is still not prepared shortly before its late start date, the project is at risk of delay and the project manager should intervene.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Late start date. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/late-start-date-pmi/
Late start date (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/late-start-date-pmi/ (retrieved 24 November 2026)
@misc{latestartdatepmi,
title = {Late start date},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/late-start-date-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/late-start-date-pmi/"> <p>Last moment at which an activity can begin without endangering the project end date or a schedule constraint.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/late-start-date-pmi/">Late start date</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.