Schedule efficiency of work performed

Concept · 2 of 9 frameworks name this concept

The ratio of earned value to planned value; a value below one shows that the project is performing work more slowly than the baseline provides for.

ConceptSchedule efficiency of work performedTopic area Monitoring and control
Preferred term
ISO 21506 · 3.84Schedule performance indexalso SPI
equivalent
PMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Schedule performance index
Concordance of the concept “Schedule efficiency of work performed”. The preferred term is the designation under which the glossary lists the concept.