Resource levelling
Definition
In resource levelling, activities are moved, split or reassigned until the load on every resource no longer exceeds its availability. If the available float is not sufficient for this, the project end date moves. A milder form, resource smoothing, only moves activities within their float and accepts that overloads may not disappear completely.
Equivalents in other frameworks
Concept Adjusting the schedule to available capacity · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Resource leveling | closely related | allows the finish date to move; resource balancing also includes smoothing within float |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Resource levelling
- Topic area
- Resources and estimating
Distinction
Resource levelling tends to lengthen the project duration, whereas schedule compression shortens it. Resource planning determines demand; levelling adapts the plan to actual availability. The critical chain method takes resource bottlenecks into account from the outset when determining the path that drives the end date.
In practice
In the schedule for introducing a laboratory information system, a single validation expert is assigned to three activities running in parallel, at 250 per cent in total. The planning software places two of the activities one after the other. One of them has enough float; the other becomes critical as a result and moves the project end by one week. The project manager checks whether a second specialist could take over the simpler parts.
Frequently asked questions
Should levelling be left to the software?
As a proposal, yes; as a decision, no. Automatic levelling takes neither priorities nor the option of distributing work differently into account.
What is the difference between levelling and smoothing?
Levelling removes overloads even at the price of a later end date; smoothing stays within the float and keeps the end date.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Resource levelling. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/resource-levelling/
Hain, D. (n.d.): Resource levelling. PMDecoder. https://pmdecoder.com/en/glossary/resource-levelling/ (retrieved 24 November 2026)
@misc{resourcelevelling,
author = {Hain, Dennis},
title = {Resource levelling},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/resource-levelling/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/resource-levelling/"> <p>Adjusting a schedule so that no resource is planned beyond its available capacity</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/resource-levelling/">Resource levelling</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.