Schedule variance

Definition

In PMI usage, schedule variance (SV) is an earned value indicator that shows how far the work performed differs from the work planned at a status date. It is calculated as earned value minus planned value. A negative value means that less work has been completed than planned, a positive value that the project is ahead of plan. Because both quantities are measured in budget units, schedule variance is also a monetary amount, not a unit of time. It can be determined for the whole project, individual control accounts or work packages.

Equivalents in other frameworks

Concept Difference between earned value and planned value · three frameworks reviewed

Equivalents of Schedule variance in other frameworks
FrameworkTerm thereRelationNote
generalSchedule varianceequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Schedule variance

Distinction

The term corresponds to the cross-framework term schedule variance in the sense of earned value analysis. The schedule performance index expresses the same relationship as a ratio. Cost variance compares earned value not with the plan but with actual cost. Anyone who needs the delay in days or weeks has to analyse the schedule or use methods such as earned schedule.

In practice

In the refurbishment of an office building, planned value at the end of April is 900,000 euros and earned value 820,000 euros. The schedule variance is therefore minus 80,000 euros. A breakdown by trade shows that almost the entire variance is due to the façade work, which started two weeks late because the scaffolding permit was delayed. The other trades are on plan.

Frequently asked questions

Why is schedule variance expressed in euros?

Because it is calculated from budget quantities. It shows the value of work that should have been completed by the status date but is still missing. A statement in days requires the schedule.

What does a schedule variance of zero at project end mean?

Not necessarily that the project finished on time. At the end all work has been performed, so earned value and planned value are equal even if completion came later.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Schedule variance. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/schedule-variance-pmi/

Short form

Schedule variance (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/schedule-variance-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{schedulevariancepmi,
  title   = {Schedule variance},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/schedule-variance-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/schedule-variance-pmi/">
  <p>Earned value minus planned value; shows in budget units whether the project is ahead of or behind plan.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/schedule-variance-pmi/">Schedule variance</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.