Risk response
Definition
In PMI terms, a risk response is the reaction selected, agreed and implemented for a risk. For threats PMI identifies the strategies escalate, avoid, transfer, mitigate and accept; for opportunities, escalate, exploit, share, enhance and accept. Escalation is appropriate when a risk lies outside the project's remit. Strategies can also be chosen for the overall uncertainty of the project. Each response includes specific actions, a named owner, dates and, where needed, budget. Its effectiveness is monitored as the project continues.
Equivalents in other frameworks
Concept Selecting and implementing risk responses · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Risk response | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Risk management
- this term
- Risk response
- Topic area
- Risks and opportunities
Distinction
The term corresponds to risk response in ISO 21506. It is the umbrella term for the individual strategies such as risk avoidance or risk mitigation. A contingency plan is a prepared response that only comes into effect when the risk occurs or is triggered. A workaround is not a planned risk response but an improvised fix.
In practice
For an IT project with limited staff, the threat “loss of the only database expert” is assessed. The team chooses mitigation: a second colleague is trained and key procedures are documented. The team lead is the owner, and the deadline is the end of next month.
Frequently asked questions
Can several strategies be combined?
Yes. A common pattern is to mitigate a risk first and keep a contingency plan with a reserve for the remaining part.
When is escalation the right risk response?
When the risk exceeds the project's authority or scope, for instance because it affects the whole programme or the organization. The responsible higher level then takes ownership of the risk.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Risk response. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-response-pmi/
Risk response (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-response-pmi/ (retrieved 24 November 2026)
@misc{riskresponsepmi,
title = {Risk response},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/risk-response-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-response-pmi/"> <p>The strategy and actions chosen by a project to respond to an individual risk or to overall project risk.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-response-pmi/">Risk response</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.