Residual risk
Definition
PMI uses the term residual risk for the risk left over once the planned responses have been put in place. Hardly any action removes a risk completely; it usually reduces probability or impact to a level the organization considers acceptable. This remainder is consciously accepted, documented and monitored further. For residual risks that could still have a noticeable effect, projects often provide contingency plans or a share of the contingency reserve. Assessing the remaining risk also shows whether a response is sufficient or whether further responses are needed to bring the risk below the organization’s thresholds.
Equivalents in other frameworks
Concept Risk remaining after responses · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Residual risk | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Risk
- this term
- Residual risk
- Topic area
- Risks and opportunities
Distinction
Residual risk corresponds to the residual risk of ISO 21506, which uses the same designation. It must be clearly separated from secondary risk, which is only caused by a risk response and is therefore a new risk, not the remainder of the original one. Both are recorded in the risk register, but for different reasons.
In practice
A data centre project addresses the risk of a power failure with an uninterruptible power supply and a standby generator. The residual risk is that both fail at the same time, for example through a maintenance error. The probability is rated very low, the impact high. The team accepts the residual risk but prepares a contingency plan with emergency contacts and a sequence for shutting down systems.
Frequently asked questions
Does a residual risk have to be documented?
Yes. Only then is it clear which risk the organization is deliberately bearing and who decided so. In addition, the residual risk may grow later if conditions change.
Who decides whether a residual risk is acceptable?
The yardstick is the organization’s risk thresholds. Within these limits the project manager can decide; beyond them, usually the sponsor or a steering body.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Residual risk. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/residual-risk-pmi/
Residual risk (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/residual-risk-pmi/ (retrieved 24 November 2026)
@misc{residualriskpmi,
title = {Residual risk},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/residual-risk-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/residual-risk-pmi/"> <p>The portion of risk that planned responses do not remove and that is knowingly accepted, recorded and kept under watch.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/residual-risk-pmi/">Residual risk</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.