Cost-reimbursable contract

also: Cost-plus contract, Cost-reimbursement contract

Definition

Under a cost-reimbursable contract, the contractor bills its documented costs and receives a mark-up on them. This can be agreed as a fixed amount, as a percentage of costs or as a performance-related incentive, for example a bonus if a target cost is undercut. The cost risk lies mainly with the client, who therefore demands insight into the costs and a say in major decisions.

Equivalents in other frameworks

Concept Contract reimbursing actual costs · three frameworks reviewed

Equivalents of Cost-reimbursable contract in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKCost-reimbursable contractequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Contract
this term
Cost-reimbursable contract

Distinction

The fixed-price contract shifts the cost risk to the contractor, the cost-reimbursable contract to the client. Under a time and materials contract, hours and materials are charged at agreed rates without the underlying costs being disclosed. A percentage mark-up on costs is considered problematic, because higher costs then also mean higher profit; some public procurement rules, for example in the USA, therefore do not permit this form.

In practice

A pharmaceutical company commissions a research institute to develop a manufacturing process whose effort nobody can estimate reliably. The parties agree on cost reimbursement with a fixed fee and a bonus if certain yield values are achieved. The institute submits time and material records every month, and the company sits on the steering committee. After a year, the contract is converted to a fixed price for the transfer into production.

Frequently asked questions

When does a cost-reimbursable contract make sense?

When the scope cannot be reliably described at the outset, for example in research, development or urgent refurbishments where the condition of the structure is unclear.

How does the client protect itself against escalating costs?

Through cost ceilings, incentives for savings, audit rights, regular reports and approvals before major expenditure.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Cost-reimbursable contract. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-reimbursable-contract/

Short form

Hain, D. (n.d.): Cost-reimbursable contract. PMDecoder. https://pmdecoder.com/en/glossary/cost-reimbursable-contract/ (retrieved 24 November 2026)

BibTeX
@misc{costreimbursablecontract,
  author  = {Hain, Dennis},
  title   = {Cost-reimbursable contract},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/cost-reimbursable-contract/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/cost-reimbursable-contract/">
  <p>Contract under which the client reimburses the costs actually incurred and also pays a fee for profit</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-reimbursable-contract/">Cost-reimbursable contract</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.