Total float

also: Total slack · abbr. TF

Definition

The total float of an activity is the difference between its late start date and its early start date, or equivalently between its late finish date and its early finish date. Once it has been used up, the successors are also at their latest limit. Total float therefore does not belong to the activity alone but to the entire path on which it lies.

Equivalents in other frameworks

Concept Scheduling flexibility relative to project completion · three frameworks reviewed

Equivalents of Total float in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKTotal floatequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Float
this term
Total float

Distinction

Free float indicates how far an activity can be postponed without delaying any successor; it is never greater than total float. Activities with a total float of zero form the critical path. If a path has negative total float, the available time is not sufficient.

In practice

When a new identity card system is introduced in a city administration, the training of the citizens' offices has a total float of fifteen days but no free float. When the training is postponed by a week, the go-live date is not at risk. However, the trial phase that immediately follows also slips by a week and then has only eight days of float left. The project management therefore informs the trial phase team immediately.

Frequently asked questions

How is total float calculated?

As late start minus early start or as late finish minus early finish. Both routes lead to the same result.

Why do activities share total float?

Because it relates to the project end. If one activity uses it up, it is no longer available to the following activities on the same path.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Total float. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/total-float/

Short form

Hain, D. (n.d.): Total float. PMDecoder. https://pmdecoder.com/en/glossary/total-float/ (retrieved 24 November 2026)

BibTeX
@misc{totalfloat,
  author  = {Hain, Dennis},
  title   = {Total float},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/total-float/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/total-float/">
  <p>Amount of time by which an activity can be postponed without delaying the project end or a specified end date</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/total-float/">Total float</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.