Backward pass
Definition
The backward pass is the second calculation step of the critical path method. It starts from the project end, either the early finish calculated in the forward pass or an imposed end date. From there, the network is traversed backwards to determine the late finish date and, after subtracting the duration, the late start date of each activity. Where an activity has several successors, the earliest of their late start dates governs, taking into account the type of dependency and any lag or lead. Comparing the results with those of the forward pass yields the float.
Equivalents in other frameworks
Concept Calculation of latest dates · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Backward pass | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Backward pass
- Topic area
- Network planning
Distinction
In substance the backward pass matches the German Rückwärtsrechnung in network planning. The forward pass delivers the early dates, the backward pass the late dates; only both together reveal the critical path. If the backward pass starts from a fixed end date earlier than the calculated finish, negative float results, indicating a plan that cannot be met.
In practice
The opening day of a trade fair is fixed. The project manager calculates backwards from the build-up day: the stand takes three days to assemble, so the stand technology must be delivered at the latest on the day before assembly starts, and it must be ordered six weeks earlier. This gives every activity a late date, and the team sees that only three days of flexibility remain for approving the stand graphics.
Frequently asked questions
Why is a backward pass needed if the forward pass already gives the project end?
The forward pass only shows when each activity can start at the earliest. How far an activity can move without jeopardizing the end date only follows from the late dates calculated in the backward pass.
Which value applies when an activity has several successors?
For a simple finish-to-start relationship, the smallest late start date among the successors counts. The activity must finish early enough for even the most urgent successor to start on time.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Backward pass. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/backward-pass-pmi/
Backward pass (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/backward-pass-pmi/ (retrieved 24 November 2026)
@misc{backwardpasspmi,
title = {Backward pass},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/backward-pass-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/backward-pass-pmi/"> <p>Calculation in the critical path method that starts at the project end and moves back through the network to find each activity’s latest dates.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/backward-pass-pmi/">Backward pass</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.