Product Breakdown Structure
Definition
In PRINCE2, the product breakdown structure is the hierarchical breakdown of the products a plan is to produce. Starting from the overall output as described in the project product description, each product is broken down into sub-products until a level suitable for the plan is reached. Products that come from outside the project, such as deliveries from other undertakings, are included as well so that dependencies become visible. The breakdown can be shown as a tree, a list or a mind map. The product descriptions and the sequence of production are derived from it; it is therefore a central step of product-based planning.
Equivalents in other frameworks
Concept Hierarchical decomposition of project scope · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Product breakdown structure | equivalent | breaks down the result into sub-products instead of the work into work packages |
| ISO 21506 | Work breakdown structure | partially overlapping | Breakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506. |
| PMI / PMBOK | Work breakdown structure | partially overlapping | Breakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506. |
| Scrum | Product Backlog | partially overlapping | also decomposes the scope, but ordered by value rather than hierarchically |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Product Breakdown Structure
- Topic area
- Planning and project structure
Distinction
The work breakdown structure usually breaks project scope down into work, the product breakdown structure into results, without naming activities. It largely corresponds to the product breakdown structure under ISO 21506. PRINCE2 does not require a particular form of presentation; management products can also be included if they are needed for planning.
In practice
For introducing an intranet, the team breaks the overall output down into three branches: technical platform, content and roll-out. Under “content” are the home page, department pages and policy collection, under “roll-out” training materials and the launch date. The existing user administration is marked as an external product because another project delivers it.
Frequently asked questions
Why are external products included?
Because the project depends on them but cannot control them itself. Making them visible allows dependencies and risks to be recognized early.
How deep should the breakdown go?
Deep enough for the lowest-level products to be described, estimated and assigned to individual teams. For the project plan a coarser level than for a stage plan is usually sufficient.
Source and context
- Reference
- PRINCE2 7, Praktik Pläne
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Product Breakdown Structure. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/
Hain, D. (n.d.): Product Breakdown Structure. PMDecoder, entry on PRINCE2 7, Praktik Pläne. https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/ (retrieved 24 November 2026)
@misc{productbreakdownstructureprince2,
author = {Hain, Dennis},
title = {Product Breakdown Structure},
note = {PMDecoder, PRINCE2 7, Praktik Pläne},
url = {https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/"> <p>Hierarchical breakdown of all products of a plan in PRINCE2, the starting point of product-based planning.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/">Product Breakdown Structure</a>, PMDecoder, PRINCE2 7, Praktik Pläne</footer> </blockquote>
Found a mistake? Let us know, we check every report.