Topic area
Scheduling
Terms relating to the schedule: activities, durations, effort, milestones, calendars and the techniques that can be used to shorten a schedule.
- ActivityISO 21506 · 3.2Defined piece of work without which a project, programme or portfolio cannot be finished; in the schedule it has a duration, start and finish.
- ActivityPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In PMI usage, a clearly delimited piece of project work that is planned in the schedule.
- Activity durationcross-frameworkTime span between the start and finish of an activity, measured in working units such as hours, days or weeks
- Activity listcross-frameworkTabular listing of all activities of a project with identifier, description, duration and dependencies
- Activity listPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In PMI usage, the register of every activity planned in a project’s schedule, each with its own identifier and a short description of the work involved.
- Activity sequence plancross-frameworkRepresentation of the logical order and dependencies of a project's activities, as yet without specific dates
- Actual datecross-frameworkThe point in time at which an activity actually started or finished, as distinct from the planned date
- Crashingcross-frameworkShortening activity durations on the critical path by adding resources, usually at higher cost
- CrashingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In PMI usage, schedule compression that brings in extra resources to cut duration, choosing the options with the lowest added cost.
- DurationPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Span of working time, counted in workdays or weeks, that an activity occupies from start to finish, with weekends and holidays left out.
- Fast trackingcross-frameworkShortening a schedule by carrying out activities originally planned in sequence fully or partly in parallel
- Fast trackingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Shortening the schedule by letting activities that would normally run one after another overlap in time; saves time but raises the risk of rework.
- Gantt chartcross-frameworkBar chart that shows the activities of a project as horizontal bars on a time axis
- Gantt chartPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Timeline view of the schedule in which each activity appears as a bar stretching from its start date to its finish date.
- High-level schedulecross-frameworkConcise schedule showing phases, milestones and main work, created early in the project and refined later
- Imposed datecross-frameworkDate set from outside that an activity or milestone must meet, for example from a contract, grant funding or an authority's deadline
- MilestoneISO 21506 · 3.37Significant point in time for a project, a programme or a portfolio, such as a decision or handover date, already scheduled or still to be fixed.
- MilestonePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Marked point in the course of a project, programme or portfolio, such as an acceptance or decision, with no duration of its own in the schedule.
- Milestone plancross-frameworkOverview of the key milestones of a project with their planned dates and the results expected at each of them
- Milestone schedulePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Condensed schedule overview listing only the milestones and their planned dates instead of individual activities, e.g. for management reports.
- Planned datecross-frameworkCurrently intended start or finish date of an activity, resulting from the schedule that is valid at the time
- Project calendarcross-frameworkCalendar that specifies for a project on which days and at which times work is carried out
- Project calendarPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Calendar in the schedule model that fixes the days and shifts on which work may be done, turning durations into concrete dates.
- Project schedulecross-frameworkPlan that specifies when the activities and milestones of a project are to start and finish
- Project schedulePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Presentation of planned project dates generated from the schedule model, for example as a Gantt chart, milestone schedule or network diagram.
- Schedule bufferISO 21506 · 3.83Reserve of time deliberately placed at chosen points in the schedule so that unexpected delays are cushioned before they hit key dates.
- Schedule compressioncross-frameworkUmbrella term for measures that shorten the planned duration of a project without reducing its scope
- Schedule compressionPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Ways of shortening a schedule's total duration while keeping the agreed scope intact.
- Schedule managementcross-frameworkPlanning, monitoring and controlling all dates of a project so that results are available on time
- Summary activitycross-frameworkActivity in the schedule that groups several subordinate activities and shows their overall time span and totals
- Summary activityPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Bar in the schedule that bundles a group of related activities and represents them as one.
Concepts in this topic area
- Bar chart representation of a scheduleThe representation of the activities of a project as horizontal bars on a time axis, often supplemented by dependencies, milestones and progress.Gantt chart · Gantt chart
- Defined piece of work with a start and finishThe smallest sequencing element of a schedule: a task with a defined start, finish and duration, which is usually derived from a work package.Activity · Activity
- Overview of key project eventsThe condensed schedule showing only the milestones with their planned dates; suitable for the steering committee, the sponsor and management reports.Milestone plan · Milestone schedule
- Rollup of several activities in the scheduleThe higher-level schedule activity that groups several subordinate activities, often as a single bar, and whose start, finish and duration derive from them.Summary activity · Summary activity
- Shortening a schedule without reducing scopeThe umbrella term for measures that shorten the planned project duration without reducing the agreed scope; the two main forms are crashing and fast tracking.Schedule compression · Schedule compression
- Shortening through additional resourcesThe schedule compression technique in which activities on the critical path are sped up through more staff, overtime or equipment, usually at extra cost.Crashing · Crashing
- Shortening through parallel workThe schedule compression technique in which activities planned in sequence are performed wholly or partly in parallel, which increases the risk of rework.Fast tracking · Fast tracking
- Significant event in the course of a projectA point in time or event without its own duration that marks significant progress in a project, such as a completed result or an upcoming decision.Milestone · Milestone
- Tabular list of all activitiesThe list of all activities of a project with identifier, description and often duration and predecessors; the starting point for network diagram and schedule.Activity list · Activity list
- Time span between start and finish of an activityThe time an activity takes from its start to its completion, measured in working days or other calendar units; not to be equated with effort.Activity duration · Duration
- Timing of project workThe plan that sets start and finish dates for the activities and milestones of a project and thus describes the project timeline in a binding way.Project schedule · Project schedule
- Working time rules of a projectThe calendar that defines on which days and at which times project work takes place; public holidays and company shutdowns feed into all schedule calculations.Project calendar · Project calendar