Topic area

Scheduling

Terms relating to the schedule: activities, durations, effort, milestones, calendars and the techniques that can be used to shorten a schedule.

31 terms

Concepts in this topic area

  • Bar chart representation of a scheduleThe representation of the activities of a project as horizontal bars on a time axis, often supplemented by dependencies, milestones and progress.Gantt chart · Gantt chart
  • Defined piece of work with a start and finishThe smallest sequencing element of a schedule: a task with a defined start, finish and duration, which is usually derived from a work package.Activity · Activity
  • Overview of key project eventsThe condensed schedule showing only the milestones with their planned dates; suitable for the steering committee, the sponsor and management reports.Milestone plan · Milestone schedule
  • Rollup of several activities in the scheduleThe higher-level schedule activity that groups several subordinate activities, often as a single bar, and whose start, finish and duration derive from them.Summary activity · Summary activity
  • Shortening a schedule without reducing scopeThe umbrella term for measures that shorten the planned project duration without reducing the agreed scope; the two main forms are crashing and fast tracking.Schedule compression · Schedule compression
  • Shortening through additional resourcesThe schedule compression technique in which activities on the critical path are sped up through more staff, overtime or equipment, usually at extra cost.Crashing · Crashing
  • Shortening through parallel workThe schedule compression technique in which activities planned in sequence are performed wholly or partly in parallel, which increases the risk of rework.Fast tracking · Fast tracking
  • Significant event in the course of a projectA point in time or event without its own duration that marks significant progress in a project, such as a completed result or an upcoming decision.Milestone · Milestone
  • Tabular list of all activitiesThe list of all activities of a project with identifier, description and often duration and predecessors; the starting point for network diagram and schedule.Activity list · Activity list
  • Time span between start and finish of an activityThe time an activity takes from its start to its completion, measured in working days or other calendar units; not to be equated with effort.Activity duration · Duration
  • Timing of project workThe plan that sets start and finish dates for the activities and milestones of a project and thus describes the project timeline in a binding way.Project schedule · Project schedule
  • Working time rules of a projectThe calendar that defines on which days and at which times project work takes place; public holidays and company shutdowns feed into all schedule calculations.Project calendar · Project calendar

All concepts compared