Risk avoidance

Definition

In PMI terms, risk avoidance is a response strategy for threats. The aim is to eliminate the threat entirely or to change the project so that the threat can no longer have an effect. Typical means are a changed scope, a different approach, dropping an unproven technology, further clarification of requirements or an adjustment of dates. In the extreme case, avoidance can mean not carrying out the project at all. The strategy is suited above all to threats with high probability and severe negative impact. PMI's counterpart for opportunities is exploiting them.

Equivalents in other frameworks

Concept Eliminating a risk · three frameworks reviewed

Equivalents of Risk avoidance in other frameworks
FrameworkTerm thereRelationNote
generalRisk avoidanceequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Risk response
this term
Risk avoidance

Distinction

The term corresponds to the cross-framework concept of risk avoidance. Risk mitigation only lowers probability or impact, whereas risk avoidance aims to bring probability to zero or cut off the impact completely. Risk transference shifts the consequences to a third party but does not remove the threat.

In practice

A project to modernize an online shop plans to use a pre-release version of a framework. The team recognizes that defects in this early version could jeopardize the launch. It decides to use the proven previous version and to introduce the new one only after launch. This removes the threat to the launch date.

Frequently asked questions

Is risk avoidance always the best choice?

No. Avoidance often has a price, such as features, time or opportunities. The strategy pays off when the threat is serious and the cost of avoiding it is acceptable.

Can avoidance create new risks?

Yes. A changed approach can bring uncertainties of its own. PMI calls such follow-on risks secondary risks; they must be recorded as well.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk avoidance. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-avoidance-pmi/

Short form

Risk avoidance (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-avoidance-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{riskavoidancepmi,
  title   = {Risk avoidance},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-avoidance-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-avoidance-pmi/">
  <p>Strategy against a threat that removes it altogether or shields the project completely from its effects.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-avoidance-pmi/">Risk avoidance</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.