Project calendar

Definition

The project calendar determines the working time a schedule calculates with: working days and non-working days, daily working hours, public holidays, company holidays and special periods such as shift operation or possession periods. Planning tools use it to calculate dates from durations. An activity with a duration of five days ends on different days depending on the calendar.

Equivalents in other frameworks

Concept Working time rules of a project · three frameworks reviewed

Equivalents of Project calendar in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKProject calendarequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project calendar
Topic area
Scheduling

Distinction

The project calendar applies to the whole project; resource calendars record the availability of individual people or machines, such as leave or part-time work. Activity calendars govern exceptions for individual activities, such as work that is only possible at weekends. An appointment diary in everyday office life, by contrast, manages meetings and has nothing to do with calculating dates.

In practice

A project to renew a railway track may only work during night-time possessions and on two extended weekends. The planner creates a separate calendar for this in which only these time windows count as working time. With the normal office calendar, the planning tool would have calculated completion after six weeks; with the possession calendar, the result is a realistic four months. In addition, the installation crews enter their holidays in resource calendars.

Frequently asked questions

Which public holidays apply in the project calendar?

Those that apply at the respective work locations. Projects spanning several federal states or countries often need several calendars.

Can a project have several calendars?

Yes. A standard calendar for the project is usual, supplemented by resource and activity calendars for exceptions.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Project calendar. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-calendar/

Short form

Hain, D. (n.d.): Project calendar. PMDecoder. https://pmdecoder.com/en/glossary/project-calendar/ (retrieved 24 November 2026)

BibTeX
@misc{projectcalendar,
  author  = {Hain, Dennis},
  title   = {Project calendar},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/project-calendar/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-calendar/">
  <p>Calendar that specifies for a project on which days and at which times work is carried out</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-calendar/">Project calendar</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.