Progress practice

Definition

The progress practice describes how a PRINCE2 project tracks and controls its progress. It builds on the principle of managing by exception: each level is given tolerances, that is permitted deviations, for example in time and cost, within which it decides for itself. If these are likely to be exceeded, the next higher level is involved. The practice distinguishes time-driven controls, such as regular reports, from event-driven ones, such as the end of a management stage or the occurrence of an exception. Comparisons are based on the approved plans; the results are forecasts and, where needed, corrective actions or an exception plan.

Equivalents in other frameworks

Concept Monitoring and controlling a project · two frameworks reviewed

Equivalents of Progress practice in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Controlclosely relatedControl through tolerances and management by exception with fixed escalation levels.
PM²Monitor & Controlclosely relateddescribed in PM² as a separate group of activities spanning all phases

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Other terms

Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.

Progress theme
deprecated

Classification

this term
Progress practice

Distinction

General project control covers monitoring and intervening without a fixed escalation model. The progress practice combines both with clearly delimited authority: the project board need not know about every deviation but is involved only when a tolerance is likely to be exceeded. It is not at odds with earned value management; that can serve as a measuring method within the practice.

In practice

An energy supplier is building a customer portal. For the second stage, the project board gives the project manager a cost tolerance of ten per cent and a time tolerance of two weeks. The project manager receives weekly updates from the teams and reports to the board every two weeks. When it becomes clear that an interface will take three weeks longer, she reports the exception immediately instead of waiting for the next regular report.

Frequently asked questions

What are tolerances for?

They define how far a level may deviate from the plan without having to consult the level above. This relieves management and speeds up everyday decisions.

What happens when a tolerance is likely to be exceeded?

The level concerned reports the situation upwards. The higher level then decides whether to order actions, request an exception plan or close the project.

Source and context

Reference
PRINCE2 7, Praktik Fortschritt
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Progress practice. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/progress-practice/

Short form

Hain, D. (n.d.): Progress practice. PMDecoder, entry on PRINCE2 7, Praktik Fortschritt. https://pmdecoder.com/en/glossary/progress-practice/ (retrieved 24 November 2026)

BibTeX
@misc{progresspractice,
  author  = {Hain, Dennis},
  title   = {Progress practice},
  note    = {PMDecoder, PRINCE2 7, Praktik Fortschritt},
  url     = {https://pmdecoder.com/en/glossary/progress-practice/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/progress-practice/">
  <p>PRINCE2 7 practice governing how progress is monitored, compared against plans and controlled through tolerances.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/progress-practice/">Progress practice</a>, PMDecoder, PRINCE2 7, Praktik Fortschritt</footer>
</blockquote>

Found a mistake? Let us know, we check every report.