Schedule compression
Definition
PMI uses schedule compression as the umbrella term for all measures that reduce the planned duration of a project or a part of it while leaving the scope unchanged. The trigger is usually a fixed end date, a milestone that has been brought forward or a delay that must be recovered. The two best-known techniques are crashing, which adds resources to selected activities, and fast tracking, which runs activities that would normally follow one another fully or partly in parallel. Compression only has an effect on activities on the critical path; speeding up other activities does not gain a single day.
Equivalents in other frameworks
Concept Shortening a schedule without reducing scope · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Schedule compression | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Schedule compression
- Narrower terms
- CrashingFast tracking
- Topic area
- Scheduling
Distinction
Schedule compression corresponds to what the glossary describes under the German term Terminplanverdichtung, and it is the umbrella term for crashing and fast tracking. Reducing scope is not part of it: removing deliverables also shortens the plan, but it changes the agreement and needs a change decision. Resource leveling often works in the opposite direction, because it moves activities to fit limited capacity.
In practice
A new warehouse is to go into operation two weeks earlier because a major customer wants deliveries to start sooner. The project manager examines the critical path and finds two options: a second installation crew can assemble the racking in half the time, and training for warehouse staff can start during the final software tests instead of afterwards. Both measures are assessed for additional cost and the added risk of rework and presented to the sponsor for a decision.
Frequently asked questions
What does schedule compression cost?
Crashing usually increases cost because more staff, overtime or more expensive resources are needed. Fast tracking costs less at first but increases risk, because work builds on results that are not yet confirmed and rework may follow.
Can any schedule be compressed at will?
No. Some activities cannot be accelerated by adding people, such as curing times or regulatory deadlines. In addition, another path may become critical after compression, so further measures have to be applied there.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Schedule compression. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/schedule-compression-pmi/
Schedule compression (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/schedule-compression-pmi/ (retrieved 24 November 2026)
@misc{schedulecompressionpmi,
title = {Schedule compression},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/schedule-compression-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/schedule-compression-pmi/"> <p>Ways of shortening a schedule's total duration while keeping the agreed scope intact.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/schedule-compression-pmi/">Schedule compression</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.