Early start date

Definition

The early start date, ES for short, is the earliest time an activity can start according to the logic of the network. It is determined in the forward pass of the critical path method: for the first activity it is the project start or the data date of the calculation, for all others it follows from the early finish dates of the predecessors, taking into account relationship type, lag and lead. If an activity has several predecessors, the latest of the resulting dates applies. Constraints such as “start no earlier than” can also push the early start date back.

Equivalents in other frameworks

Concept Earliest possible start of an activity · three frameworks reviewed

Equivalents of Early start date in other frameworks
FrameworkTerm thereRelationNote
generalEarly start dateequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Early start date

Distinction

The early start date corresponds to the German frühester Anfangszeitpunkt in network planning. The late start date, by contrast, indicates when an activity must start at the latest. The date on which the activity is actually scheduled may lie between the two, for example when resources only become available later. The real start is recorded as an actual date.

In practice

For the introduction of a new point-of-sale system in a chain of stores, the scheduling tool calculates that the rollout in the first store can start on 12 March at the earliest, because only then will the hardware have been delivered and the test phase completed. Sales had hoped for early March; the early start date provides a factual explanation of why that is not possible without changes to the plan.

Frequently asked questions

Which value applies when there are several predecessors?

For finish-to-start relationships, the latest of the early finish dates of all predecessors, plus any lag. The activity can only start when all its prerequisites are met.

Must an activity start on its early start date?

No. It can start later, up to its late start date, without jeopardizing the project end. Whether that is sensible depends on resources, risks and dependencies on its successors.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Early start date. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/early-start-date-pmi/

Short form

Early start date (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/early-start-date-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{earlystartdatepmi,
  title   = {Early start date},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/early-start-date-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/early-start-date-pmi/">
  <p>Earliest possible moment at which an activity not yet completed can begin; determined by the forward pass.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/early-start-date-pmi/">Early start date</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.