Performance measurement baseline

abbr. PMB

Definition

The performance measurement baseline brings together which work is to be done when and what budget is intended for it. It consists of the time-phased budgets of all control accounts plus the budget not yet distributed. It yields the planned value for every cut-off date, and at the end it equals the budget at completion of the project. The management reserve is explicitly excluded, so that the measurement is not distorted by funds that have not yet been assigned to any work.

Equivalents in other frameworks

Concept Time-phased baseline for performance measurement · one framework reviewed

Equivalents of Performance measurement baseline in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKPerformance measurement baselineequivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Performance measurement baseline

Distinction

Baseline is the general term for an approved reference version, often kept separately for scope, schedule and cost. The performance measurement baseline is the integrated form in which these three are inseparably linked. The overall project budget is larger because it also contains the management reserve.

In practice

A satellite project has a total budget of 85 million euros. Of this, 80 million are spread across 31 control accounts and 36 months in the performance measurement baseline, while 5 million remain with programme management as management reserve. The baseline curve shows a planned value of 26 million euros for month twelve. Every approved change, including every release from the reserve, is incorporated into the baseline in a traceable way.

Frequently asked questions

May the performance measurement baseline be changed?

Yes, but only through a defined change procedure, for example after approved scope changes or releases from the management reserve. Retroactive adjustments that make variances disappear are not permitted.

Why is the German glossary using an English term here?

No single German translation has become established in earned value management practice. The abbreviation PMB is common in reports and tools.

Source and context

Reference
ISO 21506:2024, 3.44
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Performance measurement baseline. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/performance-measurement-baseline/

Short form

Hain, D. (n.d.): Performance measurement baseline. PMDecoder, entry on ISO 21506:2024, 3.44. https://pmdecoder.com/en/glossary/performance-measurement-baseline/ (retrieved 24 November 2026)

BibTeX
@misc{performancemeasurementbaseline,
  author  = {Hain, Dennis},
  title   = {Performance measurement baseline},
  note    = {PMDecoder, ISO 21506:2024, 3.44},
  url     = {https://pmdecoder.com/en/glossary/performance-measurement-baseline/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/performance-measurement-baseline/">
  <p>Measurement basis of earned value management: the plan of work and budget spread over time, leaving out the management reserve held back.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/performance-measurement-baseline/">Performance measurement baseline</a>, PMDecoder, ISO 21506:2024, 3.44</footer>
</blockquote>

Found a mistake? Let us know, we check every report.