Start-to-finish
Definition
Start-to-finish, SF for short, is the rarest of the four logical relationships in a schedule. It specifies that the successor cannot be completed before the predecessor has started. The start of one activity thus determines the earliest finish of the other. The relationship is typical of handovers in which an existing state may only end once the new one is under way, such as shift changes or the parallel operation of an old and a new system. It can also carry a lag or lead.
Equivalents in other frameworks
Concept Finish after another activity starts · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Start-to-finish relationship | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Logical relationship
- this term
- Start-to-finish
- Topic area
- Network planning
Distinction
Start-to-finish corresponds to the German Sprungfolge in network planning. It is easily confused with finish-to-start, where the order is reversed: there, the predecessor must finish before the successor starts. Many sequences described as start-to-finish can also be modelled as finish-to-start by reversing the direction, which is often easier to understand.
In practice
When an old merchandise management system is replaced, operation of the legacy system must not end before the new system has gone live. The project manager links “new system live” as predecessor with “operate legacy system” as successor using start-to-finish. If go-live is delayed, legacy operation is extended automatically, and the cost of extending the licence becomes visible.
Frequently asked questions
Why is start-to-finish so rare?
Because most sequences are thought of in a forward direction, and handovers can often be represented with other relationship types. The relationship also seems counterintuitive to many people at first.
Do scheduling tools support start-to-finish?
The common tools offer all four relationship types. Because start-to-finish is rare, its use in a plan should be briefly explained so that others can follow it.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Start-to-finish. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/start-to-finish/
Start-to-finish (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/start-to-finish/ (retrieved 24 November 2026)
@misc{starttofinish,
title = {Start-to-finish},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/start-to-finish/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/start-to-finish/"> <p>Rarest type of dependency in a schedule: the successor may only be completed after the predecessor has begun, as with shift handovers.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/start-to-finish/">Start-to-finish</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.