Risk breakdown structure

Definition

The risk breakdown structure (RBS) arranges the possible sources of risk in a hierarchy. At the top level there are broad areas, such as technical, organizational, commercial and external sources; below they are refined step by step, for example into requirements, technology, suppliers, regulations or weather. PMI uses the RBS mainly as a framework for risk identification, so that no sources are overlooked, and as a basis for risk categories. It can be defined organization-wide and tailored for each project, and is often specified in the risk management plan.

Equivalents in other frameworks

Concept Hierarchical breakdown of risk sources · three frameworks reviewed

Equivalents of Risk breakdown structure in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Risk breakdown structureequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Risk breakdown structure

Distinction

The term corresponds to the risk breakdown structure in ISO 21506. Unlike the work breakdown structure, the RBS does not break down work but cause areas. The risk register contains individual risks; the RBS provides the structure into which they can be slotted.

In practice

A municipal administration is preparing to move into a new office building. The project manager uses the RBS provided by the project management office, with the main branches technology, organization, legal and environment, and adds “public participation” to the environment branch. In the risk workshop, the team goes through the branches one by one and assigns each risk it finds to a branch.

Frequently asked questions

Does every project need its own RBS?

Not necessarily. Many organizations provide a standard RBS. The project adopts it and tailors it to its particular circumstances.

How does the RBS help with evaluation?

When risks are assigned to branches, it becomes visible where they cluster. This helps to tackle causes together instead of treating each risk separately.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk breakdown structure. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/

Short form

Risk breakdown structure (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{riskbreakdownstructurepmi,
  title   = {Risk breakdown structure},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/">
  <p>Layered classification of conceivable risk sources, e.g. technical, organizational, commercial and external, used as a grid for identifying risks.</p>