Corrective action
Definition
Corrective actions respond to variances that have already been identified. ISO 21506 gives the term two meanings. In project and programme management, a corrective action redirects ongoing work so that performance is brought back into line with the plan, for example additional staff, a changed sequence of work, rework on a faulty result or renegotiating a delivery date. In quality management, it aims to remove the cause of a defect so that it does not happen again.
Equivalents in other frameworks
Concept Action against an occurred deviation · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Corrective action | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Corrective action
- Topic area
- Monitoring and control
Distinction
A corrective action addresses a variance that has occurred, a preventive action a possible one. Quality management also distinguishes between a correction, which fixes the defect itself, and a corrective action, which removes its cause. A fallback action is triggered when a known risk occurs and is planned in advance.
In practice
The approval test for a new power tool fails because a cable does not pass the strain relief test. As a correction, the prototypes already built are modified. As a corrective action, the design team changes the cable routing and extends the internal test specification so that the problem is spotted earlier on future devices. The project manager schedules both steps with effort and dates and informs the steering committee about the later market launch.
Frequently asked questions
Who decides on corrective actions?
The project manager within their authority; the client if agreed objectives are affected.
How do you check whether a corrective action works?
By measuring after a defined period whether the variance has disappeared and does not come back.
Source and context
- Reference
- ISO 21506:2024, 3.15 und 3.16
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Corrective action. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/corrective-action/
Hain, D. (n.d.): Corrective action. PMDecoder, entry on ISO 21506:2024, 3.15 und 3.16. https://pmdecoder.com/en/glossary/corrective-action/ (retrieved 24 November 2026)
@misc{correctiveaction,
author = {Hain, Dennis},
title = {Corrective action},
note = {PMDecoder, ISO 21506:2024, 3.15 und 3.16},
url = {https://pmdecoder.com/en/glossary/corrective-action/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/corrective-action/"> <p>Action that remedies a variance that has already occurred; in quality management, removing the cause of a defect so that it does not recur.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/corrective-action/">Corrective action</a>, PMDecoder, ISO 21506:2024, 3.15 und 3.16</footer> </blockquote>
Found a mistake? Let us know, we check every report.