Product Backlog
Definition
The Product Backlog collects everything that, according to current knowledge, should make a product better, and puts it in order. It is the only place from which a Scrum Team takes its work. The list is never complete: new insights from Sprint Reviews, from users or from the market lead to new, changed or deleted items. At the top are the items that are clear and small enough for the team to complete within one Sprint. The Product Goal is part of the Product Backlog and gives it direction. The Product Owner is accountable for content and order; the Developers estimate the size of the items.
Equivalents in other frameworks
Concept Hierarchical decomposition of project scope · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Work breakdown structure | partially overlapping | also decomposes the scope, but ordered by value rather than hierarchically |
| ISO 21506 | Product breakdown structure | partially overlapping | breaks down the result into sub-products instead of the work into work packages |
| PMI / PMBOK | Work breakdown structure | partially overlapping | also decomposes the scope, but ordered by value rather than hierarchically |
| PRINCE2 | Product Breakdown Structure | partially overlapping | Breakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Scrum Artifact
- this term
- Product Backlog
- Narrower term
- Product Backlog item
- Topic area
- Planning and project structure
Distinction
A work breakdown structure divides the project scope hierarchically and as completely as possible at the outset. The Product Backlog, by contrast, is ordered by value and urgency and is continuously updated. A requirements specification describes requirements as a contractual basis; the Product Backlog is a working tool that may change with every Sprint. The Sprint Backlog contains only the part that the Developers have selected for the current Sprint.
In practice
For software that plans duty rosters in care homes, the Product Backlog contains around 120 items. At the top are well-described points such as swapping shifts between two nurses; further down are rough ideas such as a link to payroll. After a change in the law on rest periods, the Product Owner moves the check of the minimum rest period to the top, and the team refines the item in the following week.
Frequently asked questions
Who may add items to the Product Backlog?
Suggestions can come from anyone, including stakeholders. However, the Product Owner is accountable for content and order and may delegate the creation of items.
Must the Product Backlog be complete before work begins?
No. It is enough if the top items are clear enough for the next Sprint. The rest emerges and changes as the work proceeds.
Source and context
- Reference
- Scrum Guide 2020, Abschnitt Product Backlog
- Edition
- Scrum Guide 2020
- Author
- Dennis Hain
Differences from other editions
- Scrum Guide 2017
- The guide did not treat a Product Goal as a fixed part of the Product Backlog. The list gathered everything to be changed in the product for future releases, from new features and requirements to improvements and bug fixes, and at least at every Sprint Review the Product Owner checked how much work was still open towards a goal.
Cite this entry
Hain, D. (n.d.). Product Backlog. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/product-backlog/
Hain, D. (n.d.): Product Backlog. PMDecoder, entry on Scrum Guide 2020, Abschnitt Product Backlog. https://pmdecoder.com/en/glossary/product-backlog/ (retrieved 24 November 2026)
@misc{productbacklog,
author = {Hain, Dennis},
title = {Product Backlog},
note = {PMDecoder, Scrum Guide 2020, Abschnitt Product Backlog},
url = {https://pmdecoder.com/en/glossary/product-backlog/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/product-backlog/"> <p>Ordered, continuously evolving list of all work intended to improve a product, and the Scrum Team's single source of work</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/product-backlog/">Product Backlog</a>, PMDecoder, Scrum Guide 2020, Abschnitt Product Backlog</footer> </blockquote>
Found a mistake? Let us know, we check every report.