Gantt chart

Definition

In PMI usage, a Gantt chart is a bar chart that presents schedule information. Activities appear one below the other on the vertical axis, time runs horizontally, and each duration appears as a bar between the start and finish dates. Dependencies are often shown as arrows, milestones as diamonds and progress as a filled portion of the bar. PMI regards the Gantt chart as one of several ways of presenting the project schedule, alongside milestone charts and network diagrams. It is well suited to reports because it can be read without specialist knowledge.

Equivalents in other frameworks

Concept Bar chart representation of a schedule · three frameworks reviewed

Equivalents of Gantt chart in other frameworks
FrameworkTerm thereRelationNote
generalGantt chartequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Gantt chart
Topic area
Scheduling

Distinction

The cross-framework Gantt chart refers to the same thing; this entry gives the PMI view. The project schedule is the content, the Gantt chart one way of presenting it. A network diagram shows the logical relationships more clearly, while a milestone schedule condenses the plan to a few events.

In practice

For the monthly steering committee meeting, the project office produces a Gantt chart from the planning tool showing the twelve most important summary activities. A vertical line marks the data date, and the original plan is shown as a pale bar beneath the current one. Members can thus see at a glance that the migration is three weeks behind the baseline.

Frequently asked questions

Does a Gantt chart show the critical path?

Not by itself, but most planning tools can highlight critical activities in colour. The calculation itself is based on the schedule model and its dependencies, not on the chart.

What are the limits of a Gantt chart?

With very many activities it becomes cluttered, and dependencies are hard to follow. For decision-making bodies, a condensed version at the level of summary activities or milestones is therefore often worthwhile.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Gantt chart. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/gantt-chart-pmi/

Short form

Gantt chart (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/gantt-chart-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{ganttchartpmi,
  title   = {Gantt chart},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/gantt-chart-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/gantt-chart-pmi/">
  <p>Timeline view of the schedule in which each activity appears as a bar stretching from its start date to its finish date.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/gantt-chart-pmi/">Gantt chart</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.