Late finish date
also: Late finish · abbr. LF
Definition
The late finish date, LF for short, is determined in the backward pass. For the last activity, it is the target date of the project. For all others, it is derived from the earliest of the late start dates of their successors, less any time intervals. It marks the limit by which a piece of work must be done for the overall schedule to hold.
Equivalents in other frameworks
Concept Latest allowable finish of an activity · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Late finish date | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Late finish date
- Topic area
- Network planning
Distinction
The early finish date gives the earliest possible finish, the late finish the latest permissible one; their difference corresponds to the total float. A contractually agreed delivery date may lie before the calculated late finish and is then decisive as a date constraint.
In practice
For a wedding reception with 120 guests, an agency plans backwards from the day of the celebration. The table decorations must be in place the evening before, so the flowers must be delivered on the morning of the previous day. Because the florist needs two weeks' notice, the late finish of the order lies two weeks before the celebration. The agency realises that the couple must have chosen the colours by then and schedules a consultation in good time.
Frequently asked questions
How is the late finish date calculated?
For finish-to-start relationships, as the smallest late start date of all successors, each less any time interval.
How does the late finish date differ from a submission deadline?
The late finish is a calculated result from the network schedule, a submission deadline is an agreement. If the agreement is earlier, it applies.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Late finish date. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/late-finish-date/
Hain, D. (n.d.): Late finish date. PMDecoder. https://pmdecoder.com/en/glossary/late-finish-date/ (retrieved 24 November 2026)
@misc{latefinishdate,
author = {Hain, Dennis},
title = {Late finish date},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/late-finish-date/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/late-finish-date/"> <p>Latest point in time by which an activity must be completed so that neither its successors nor the project end are delayed</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/late-finish-date/">Late finish date</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.