Change control board
also: Change board · abbr. CCB
Definition
A change control board concentrates the decisions on changes that go beyond the authority of the project manager. Its members are usually representatives of the sponsor, the project manager, affected departments and, where relevant, contractors. It meets regularly or as required, assesses change requests on the basis of prepared impact analyses and records its decisions in writing.
Equivalents in other frameworks
Concept Body deciding on changes · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Change control board | equivalent | — |
| PRINCE2 | Change Authority | closely related | Can also be a single person; authority derived from and limited by the Project Board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Change control board
- Topic area
- Monitoring and control
Distinction
The steering committee directs the project as a whole, the change control board deals only with changes; in smaller projects the steering committee takes on this task as well. In IT operations there are comparable bodies for changes to live systems that work independently of projects. Change control is the procedure; the board is one decision-making body within it.
In practice
During the renewal of a public transport operator's control system, change requests from operations, engineering and safety converge. A change control board meets every two weeks. Every request must first be assessed by the affected subprojects, otherwise it is deferred. Within one year the board handles some eighty requests. The decision log later serves at acceptance as evidence of why the system deviates from the original requirements specification.
Frequently asked questions
Who should sit on the change control board?
People who can assess impacts and take binding decisions, typically the sponsor, the project manager and those responsible for the affected areas.
What happens to urgent changes?
An expedited procedure should be defined for emergencies, for example a decision by two named members with subsequent confirmation by the board.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Change control board. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/change-control-board/
Hain, D. (n.d.): Change control board. PMDecoder. https://pmdecoder.com/en/glossary/change-control-board/ (retrieved 24 November 2026)
@misc{changecontrolboard,
author = {Hain, Dennis},
title = {Change control board},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/change-control-board/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/change-control-board/"> <p>Body that reviews change requests in a project and decides whether to approve, reject or defer them</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/change-control-board/">Change control board</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.