PERT
Definition
PERT, the Program Evaluation and Review Technique, was developed in the United States in the late 1950s for a large defence programme involving many novel tasks. Each duration is estimated with an optimistic, a most likely and a pessimistic value. These yield a weighted expected value and a variance. By summing the expected values and the variances along the critical path, it is possible to estimate the probability of meeting an end date. Classically, PERT works with event-oriented network schedules.
Equivalents in other frameworks
Concept Schedule estimation with three values per activity · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Program evaluation and review technique | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- PERT
- Topic area
- Network planning
Distinction
The critical path method works with fixed durations, PERT with ranges. The estimates come from three-point estimating, on which PERT builds a complete planning method. A Monte Carlo simulation considers all paths at the same time and thus avoids a known weakness of PERT: underestimating the effect of several near-critical paths converging.
In practice
A research institute plans to build a prototype with twelve activities, some of which are being carried out for the first time. For each activity, the experts provide three estimates. The calculation gives an expected value of 38 weeks for the critical path with a standard deviation of three weeks. The funding body asks for a reliable date; the institute states 44 weeks, which according to this calculation will be met with high probability.
Frequently asked questions
How does PERT calculate the expected value?
As the optimistic value plus four times the most likely value plus the pessimistic value, divided by six. The standard deviation is approximated as the difference between the pessimistic and optimistic values, divided by six.
Is PERT still used today?
The full method rarely, but its estimating approach frequently, often in combination with simulations.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). PERT. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/pert/
Hain, D. (n.d.): PERT. PMDecoder. https://pmdecoder.com/en/glossary/pert/ (retrieved 24 November 2026)
@misc{pert,
author = {Hain, Dennis},
title = {PERT},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/pert/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/pert/"> <p>Network planning technique that describes activity durations with three estimates and derives expected values and probabilities for dates</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/pert/">PERT</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.