RASCI
Definition
RASCI is the form of responsibility assignment matrix (RAM) that PM² uses to clarify roles and responsibilities for individual activities and artefacts. The letters stand for Responsible (does the work), Accountable (ultimately answerable for correct and complete execution), Supports (works in a supporting capacity), Consulted (asked for advice, with two-way communication) and Informed (kept up to date on progress). For each task there is only one party responsible for doing it and one that is accountable. The guide contains a RASCI assignment to the standard roles for every artefact and every activity.
Equivalents in other frameworks
Concept Assigning responsibilities to tasks · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Responsibility assignment matrix | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| PMI / PMBOK | Responsibility assignment matrix | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- RASCI
- Topic area
- Project organization
Distinction
The widely used RACI has no supporting role; RASCI explicitly separates contributing work (Supports) from advice (Consulted). The Project Stakeholder Matrix lists the people involved, whereas RASCI assigns them responsibility for specific tasks.
In practice
For the Business Case, the RASCI table in the guide shows: the Project Owner is accountable, the Business Manager prepares it, the Solution Provider and the Project Manager support, the Project Steering Committee and the User Representatives are consulted, and the governance body is informed. A project adopts this table and adapts it to its own staffing.
Frequently asked questions
How is RASCI pronounced?
The guide gives the pronunciation “rasky”.
For which tasks does the guide contain RASCI tables?
For every artefact of the Initiating, Planning and Closing Phases and for every activity of execution and of Monitor & Control.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 4.12
- Edition
- PM² Guide 3.1
Cite this entry
RASCI. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/rasci/
RASCI (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.12. https://pmdecoder.com/en/glossary/rasci/ (retrieved 24 November 2026)
@misc{rasci,
title = {RASCI},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.12},
url = {https://pmdecoder.com/en/glossary/rasci/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/rasci/"> <p>Responsibility matrix in PM² that specifies for each task who performs, is accountable, supports, is consulted or is informed</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/rasci/">RASCI</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.12</footer> </blockquote>
Found a mistake? Let us know, we check every report.