Estimate at completion
abbr. EAC
Definition
The estimate at completion connects past and future: it adds the actual cost already incurred to the cost still expected for the remaining work. The remaining cost can be re-estimated by those responsible or extrapolated from performance figures, for example by dividing the remaining budget by the cost performance index. Which approach fits depends on whether the variances so far are considered one-off or lasting. It can be produced for a whole project or programme just as well as for a control account, a single work package or an activity.
Equivalents in other frameworks
Concept Expected total cost at completion · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Estimate at completion | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Estimate at completion
- Topic area
- Monitoring and control
Distinction
Budget at completion describes what the work should cost according to plan, the estimate at completion what it is likely to cost. The difference is the variance at completion. The estimate to complete covers only the share for the work still outstanding.
In practice
The refurbishment of an office building has a budget at completion of 2.4 million euros. Halfway through the work, 1.4 million euros have been spent and earned value is 1.2 million euros. If cost efficiency stayed the same, extrapolation would give 2.8 million euros. The site management, however, considers the extra costs of the structural work to be a one-off, re-estimates the remaining work at 1.15 million euros and reports an estimate at completion of 2.55 million euros, with reasons.
Frequently asked questions
How often is the estimate at completion updated?
In every reporting period, usually monthly. A thorough reassessment of the remaining work makes sense above all after significant changes or after risks have materialized.
Which formula is the right one?
None applies universally. Extrapolating with the cost performance index assumes that past efficiency will continue; a fresh estimate of the remaining work takes more effort but reflects known changes.
Source and context
- Reference
- ISO 21506:2024/Amd 1:2026, 3.25
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Estimate at completion. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/estimate-at-completion/
Hain, D. (n.d.): Estimate at completion. PMDecoder, entry on ISO 21506:2024/Amd 1:2026, 3.25. https://pmdecoder.com/en/glossary/estimate-at-completion/ (retrieved 24 November 2026)
@misc{estimateatcompletion,
author = {Hain, Dennis},
title = {Estimate at completion},
note = {PMDecoder, ISO 21506:2024/Amd 1:2026, 3.25},
url = {https://pmdecoder.com/en/glossary/estimate-at-completion/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/estimate-at-completion/"> <p>Forecast of the total cost a project, a programme or part of one will have incurred once all its work is finished, based on the current position.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/estimate-at-completion/">Estimate at completion</a>, PMDecoder, ISO 21506:2024/Amd 1:2026, 3.25</footer> </blockquote>
Found a mistake? Let us know, we check every report.