Fast tracking
Definition
In fast tracking, activities that would normally wait for one another are started at the same time or carried out with an overlap. A typical example is starting implementation before design is fully complete, or starting tests while development is still under way. The technique only works for discretionary dependencies; mandatory dependencies cannot be removed.
Equivalents in other frameworks
Concept Shortening through parallel work · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Fast tracking | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Schedule compression
- this term
- Fast tracking
- Topic area
- Scheduling
Distinction
Like crashing, fast tracking is a schedule compression technique. Initially it costs no extra money, but it increases the risk of rework, because later work builds on provisional results. Simultaneous engineering in product development is based on the same principle, but is designed as a permanent way of working rather than a short-term measure.
In practice
So that an online shop can go live in time for the Christmas season, the agency starts technical implementation when only two thirds of the design have been approved. The basic page structure is built in parallel with the last design rounds. Two page types have to be adjusted again after final approval, which costs four days of rework. Overall, the project gains three weeks and keeps its launch date.
Frequently asked questions
Which activities are suitable for fast tracking?
Those with discretionary dependencies and stable interim results, where later changes cause little rework.
How can the risk be limited?
By agreeing on stable interfaces early, keeping communication paths between the parallel teams short and allowing a time reserve for the rework that is to be expected.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Fast tracking. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/fast-tracking/
Hain, D. (n.d.): Fast tracking. PMDecoder. https://pmdecoder.com/en/glossary/fast-tracking/ (retrieved 24 November 2026)
@misc{fasttracking,
author = {Hain, Dennis},
title = {Fast tracking},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/fast-tracking/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/fast-tracking/"> <p>Shortening a schedule by carrying out activities originally planned in sequence fully or partly in parallel</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/fast-tracking/">Fast tracking</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.