Quality Management Approach
Definition
The quality management approach describes how a PRINCE2 project puts the quality practice into effect. It names the applicable quality standards and procedures, such as requirements of the organization, the customer or relevant standards, and specifies how quality checks are planned, carried out and documented. It also records who is responsible for quality in the project, which tools are used and how quality assurance outside the project is involved. The approach is created during initiation on the basis of the quality expectations in the project product description and becomes part of the project initiation documentation. The quality criteria of individual products, by contrast, are set out in their product descriptions.
Equivalents in other frameworks
Concept Setting quality objectives and checks · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Quality management plan | partially overlapping | denotes the document in which the result of quality planning is recorded |
| Six Sigma | Control plan | partially overlapping | Sets monitoring and reactions for a running process after the project, not quality assurance of the project results. |
| general | Quality planning | partially overlapping | Defines standards, procedures and responsibilities; the quality criteria of individual products are in the product descriptions. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Quality Management Approach
- Topic area
- Quality
Distinction
The PMI quality management plan has a similar purpose. An organization’s quality manual applies to all undertakings, the quality management approach only to the one project, and it can refer to the manual. It describes rules, not the results of individual checks.
In practice
A medical technology manufacturer is developing a new blood pressure monitor. The quality management approach refers to the company’s certified quality management system and the regulatory requirements for medical devices. It specifies that every design document is checked by a second person, that the clinical evaluation is reviewed by an external body and that the quality department carries out spot checks on compliance.
Frequently asked questions
Who approves the quality management approach?
The project board, as part of the project initiation documentation. The senior user makes sure that the users’ quality expectations are covered.
Does a project have to develop its own quality standards?
Usually not. The approach builds on existing standards of the organization or the customer and only adds what applies additionally to the project.
Source and context
- Reference
- PRINCE2 7, Praktik Qualität
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Quality Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/quality-management-approach/
Hain, D. (n.d.): Quality Management Approach. PMDecoder, entry on PRINCE2 7, Praktik Qualität. https://pmdecoder.com/en/glossary/quality-management-approach/ (retrieved 24 November 2026)
@misc{qualitymanagementapproach,
author = {Hain, Dennis},
title = {Quality Management Approach},
note = {PMDecoder, PRINCE2 7, Praktik Qualität},
url = {https://pmdecoder.com/en/glossary/quality-management-approach/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/quality-management-approach/"> <p>PRINCE2 management product defining the standards, procedures and responsibilities used to assure the quality of the products.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/quality-management-approach/">Quality Management Approach</a>, PMDecoder, PRINCE2 7, Praktik Qualität</footer> </blockquote>
Found a mistake? Let us know, we check every report.