Topic area
Network planning
Terms of network planning: network diagram types, logical relationships, earliest and latest dates, float and the critical path as the basis for dates.
- Activity-on-arrow networkcross-frameworkForm of network schedule in which activities are shown as arrows and the points in time between them as nodes
- Activity-on-node networkcross-frameworkForm of network schedule in which activities are shown as nodes and their dependencies as connecting arrows
- Backward passcross-frameworkCalculation of the latest permissible finish and start dates of all activities, working from the project end against the dependencies
- Backward passPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Calculation in the critical path method that starts at the project end and moves back through the network to find each activity’s latest dates.
- Critical activitycross-frameworkActivity without scheduling latitude whose delay has a direct effect on the project end
- Critical chain methodcross-frameworkPlanning method that takes resource bottlenecks into account and pools the safety margins of individual activities in shared buffers
- Critical chain methodPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Scheduling method that accounts for scarce resources and pools safety time into shared buffers on paths.
- Critical pathISO 21506 · 3.18Sequence of activities in the network schedule without float whose total duration determines the earliest finish of a project or phase.
- Critical pathPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)The chain of activities that takes longest from start to finish and therefore fixes the minimum time the project can take.
- Critical path activityPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Activity on the critical path; any delay to it immediately moves the project end date.
- Critical path methodcross-frameworkCalculation method of the network planning technique that determines dates, float and the critical path from durations and dependencies
- Critical path methodPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Calculation technique that derives early and late dates, float and the critical path from durations and dependencies.
- Dummy activitycross-frameworkActivity without duration or resources that serves only to represent dependencies correctly in an activity-on-arrow network
- Early finish datecross-frameworkEarliest possible point in time at which an activity can be completed if it starts on its early start date
- Early finish datePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Earliest possible moment at which an activity not yet completed can end; determined by the forward pass.
- Early start datecross-frameworkEarliest possible point in time at which an activity can start if all predecessors are completed on schedule
- Early start datePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Earliest possible moment at which an activity not yet completed can begin; determined by the forward pass.
- Finish-to-finishPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Schedule link in which the end of the predecessor is a precondition for the end of the successor; the starts of both remain free.
- Finish-to-finish relationshipcross-frameworkLogical relationship in which an activity can finish at the earliest once another activity has finished
- Finish-to-startPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Most common schedule link: the successor can begin at the earliest once the predecessor is complete, so one thing follows the other.
- Finish-to-start relationshipcross-frameworkLogical relationship in which an activity can only start once its predecessor has finished
- Floatcross-frameworkAmount of time by which an activity can be postponed or extended without affecting its successors or the project end
- Forward passcross-frameworkCalculation of the earliest possible start and finish dates of all activities, working from the project start along the dependencies
- Forward passPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Calculation in the critical path method that starts at the project beginning and moves forward through the network to find each activity’s earliest dates.
- Free floatcross-frameworkScheduling latitude an activity can use without any of its direct successors being pushed back
- Free floatPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Leeway an activity has relative to its immediate successors: how far it can shift before any of them has to start later.
- Lagcross-frameworkWaiting time that must elapse between an activity and its successor; in a network schedule, a positive time interval
- LagPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Waiting time built into a schedule link that pushes the start or finish of the successor back relative to its predecessor.
- Late finish datecross-frameworkLatest point in time by which an activity must be completed so that neither its successors nor the project end are delayed
- Late finish datePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Last moment at which an activity can end without endangering the project end date or a schedule constraint.
- Late start datecross-frameworkLatest point in time at which an activity may start without endangering the planned project end
- Late start datePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Last moment at which an activity can begin without endangering the project end date or a schedule constraint.
- LeadISO 21506 · 3.33Negative time offset on a dependency that allows a successor to start or finish earlier than the link would otherwise permit.
- LeadPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Advance on a schedule link that lets the successor begin earlier than the relationship alone would allow; often entered as a negative lag.
- Logical relationshipcross-frameworkDefined time dependency between two activities that determines when one may start or finish in relation to the other
- Logical relationshipPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Schedule link that defines how the start or finish of one activity depends on another activity or on a milestone.
- Network planning techniquecross-frameworkMethod for analysing, representing and calculating the flow of a project on the basis of activities and their dependencies
- Network scheduleISO 21506 · 3.38Graphical representation of a project's activities and their dependencies as a network of nodes and connecting arrows.
- PERTcross-frameworkNetwork planning technique that describes activity durations with three estimates and derives expected values and probabilities for dates
- Precedence diagramming methodPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Scheduling technique that draws activities as boxes (nodes) and connects them with arrows for their logical dependencies.
- Predecessor activitycross-frameworkActivity that comes immediately before another in the sequence and on which that activity depends through a logical relationship
- Predecessor activityPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In a schedule, the activity on which a dependent activity logically relies and whose timing shapes that activity's dates.
- Program evaluation and review techniquePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Estimating method that combines optimistic, most likely and pessimistic durations into a weighted value to reflect schedule uncertainty.
- Project schedule network diagramPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Diagram that shows a project's activities and the dependencies between them in their logical order.
- Start-to-finishPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Rarest type of dependency in a schedule: the successor may only be completed after the predecessor has begun, as with shift handovers.
- Start-to-finish relationshipcross-frameworkRarely used logical relationship in which an activity can finish at the earliest once another activity has started
- Start-to-startPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Type of dependency in which the successor may begin once the predecessor has begun; both can then run in parallel.
- Start-to-start relationshipcross-frameworkLogical relationship in which an activity can start at the earliest once another activity has started
- Subnetworkcross-frameworkSection of a network schedule that represents a defined part of the project and is linked to the overall network through interfaces
- Successor activitycross-frameworkActivity that immediately follows another in the sequence and depends on it in time
- Successor activityPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Schedule activity whose start or finish is tied to a preceding activity through a logical dependency.
- Theory of Constraintscross-frameworkManagement approach holding that a system's performance is determined by its tightest constraint, on which all improvement should focus
- Total floatcross-frameworkAmount of time by which an activity can be postponed without delaying the project end or a specified end date
- Total floatPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)An activity's total slack: how far it may be moved or extended before the project end or a fixed date is put at risk.
Concepts in this topic area
- Activity on which another dependsThe activity that immediately precedes another in the sequence and is linked to it by a logical relationship; its dates affect the successor.Predecessor activity · Predecessor activity
- Activity that depends on anotherThe activity that immediately follows another in the sequence and depends on its start or finish through a logical relationship in the schedule.Successor activity · Successor activity
- Activity without scheduling flexibilityAn activity on the critical path that has no float or scheduling flexibility, so that any delay to it immediately moves the end date of the whole project.Critical activity · Critical path activity
- Brought-forward start relative to the predecessorThe time by which a successor may start before its predecessor finishes; in the network diagram, a negative time interval between two activities.Lead · Lead
- Calculation method for dates and floatThe network planning method that calculates earliest and latest dates, float and the critical path from activity durations and dependencies.Critical path method · Critical path method
- Calculation of earliest datesThe network planning calculation step that determines the earliest start and finish dates of all activities from the project start along the dependencies.Forward pass · Forward pass
- Calculation of latest datesThe network planning calculation step that determines the latest allowable finish and start dates from the project end against the dependencies.Backward pass · Backward pass
- Diagram of activities and their dependenciesThe representation of the activities of a project as a network of nodes and arrows that shows the order in which pieces of work depend on each other.Network schedule · Project schedule network diagram
- Earliest possible finish of an activityThe earliest point in time at which an activity can be completed if it starts at its earliest start date; calculated in the forward pass through the network.Early finish date · Early finish date
- Earliest possible start of an activityThe earliest point in time at which an activity can start if all predecessors finish on schedule; result of the forward pass in the network diagram.Early start date · Early start date
- Finish after another activity finishesThe logical relationship in which an activity can finish only once another has finished, such as acceptance tests only after documentation is complete.Finish-to-finish relationship · Finish-to-finish
- Finish after another activity startsThe rarely used logical relationship in which an activity can finish only once another has started, such as legacy operation until the new system goes live.Start-to-finish relationship · Start-to-finish
- Latest allowable finish of an activityThe latest point in time by which an activity must be finished so that neither successors nor the project end are delayed; result of the backward pass.Late finish date · Late finish date
- Latest allowable start of an activityThe latest point in time at which an activity may start without jeopardizing the planned project end; result of the backward pass in the network diagram.Late start date · Late start date
- Longest sequence of activities without floatThe chain of activities in the network diagram that has no scheduling flexibility and therefore determines the earliest possible end of a project or phase.Critical path · Critical path
- Network diagram with activities on nodesThe widely used form of network diagram in which each activity is a node and arrows represent the logical relationships between the activities.Activity-on-node network · Precedence diagramming method
- Schedule estimation with three values per activityThe network planning technique that sets an optimistic, a most likely and a pessimistic duration for each activity and derives schedule probabilities from them.PERT · Program evaluation and review technique
- Scheduling dependency between two activitiesThe defined link between two activities that determines when one may start or finish relative to the other; four basic types are distinguished.Logical relationship · Logical relationship
- Scheduling flexibility relative to project completionThe time by which an activity can be delayed from its early start or extended without delaying the end of the project or breaching a fixed finish date.Total float · Total float
- Scheduling flexibility relative to successorsThe amount of time by which an activity can be delayed without pushing back the earliest start of any of its immediate successors in the schedule.Free float · Free float
- Scheduling with aggregated buffersThe planning method that takes resource constraints into account and moves safety time from individual activities into shared buffers at the end of the chain.Critical chain method · Critical chain method
- Start after another activity startsThe logical relationship in which an activity can start at the earliest once another has started; typical of coupled work running in parallel.Start-to-start relationship · Start-to-start
- Start after the predecessor finishesThe most common logical relationship: an activity can start only when its predecessor has finished, such as painting only after the plastering is complete.Finish-to-start relationship · Finish-to-start
- Waiting time between predecessor and successorThe time that must elapse between the finish of an activity and the start of its successor, such as drying times; in the network diagram, a positive interval.Lag · Lag