Cost performance index
Definition
The cost performance index, abbreviated CPI, measures in PMI’s earned value method how economically the work so far has been performed. It is obtained by dividing earned value by actual cost. A value of 1 means that the work was performed at exactly the budgeted cost. If the CPI is below 1, more was spent on the work performed than planned; above 1 there is an underrun. The cumulative CPI is considered a comparatively stable early indicator and often serves as the basis for forecasting total cost.
Equivalents in other frameworks
Concept Cost efficiency of work performed · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Cost performance index | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Cost performance index
- Topic area
- Monitoring and control
Distinction
The PMI term is equivalent to the cross-framework “Kostenleistungsindex” (cost performance index), the lead term of the concept in the glossary. Cost variance expresses the same relationship as a difference in monetary units, the CPI as a ratio. The schedule performance index measures schedule efficiency, not cost. The to-complete performance index shows what efficiency would be needed for the remaining work.
In practice
In an IT project, earned value after four months is 180,000 euros and actual cost is 200,000 euros. The CPI is 0.9: for every euro spent, 90 cents of planned work was performed. With a budget at completion of 600,000 euros, the forecast at unchanged efficiency is around 667,000 euros.
Frequently asked questions
At what CPI should action be taken?
The organization defines this through thresholds. Many projects investigate causes as soon as the cumulative CPI is noticeably below 1 and take action if the value declines over several reporting periods.
Is a CPI above 1 always good?
Not necessarily. It may indicate economical work, but also overly generous budgets, late-posted costs or overstated progress. Striking values should therefore be investigated.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Cost performance index. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-performance-index-pmi/
Cost performance index (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/cost-performance-index-pmi/ (retrieved 24 November 2026)
@misc{costperformanceindexpmi,
title = {Cost performance index},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/cost-performance-index-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/cost-performance-index-pmi/"> <p>Cost efficiency indicator obtained by dividing earned value by actual cost (CPI = EV / AC).</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-performance-index-pmi/">Cost performance index</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.