Risk threshold

Definition

In PMI terms, the risk threshold defines the level of risk exposure at which action is required. If a risk or the overall uncertainty lies above it, responses are needed; below it, the risk may be accepted. Thresholds are expressed for individual objectives, for example as an allowable deviation from the end date or the budget, and are derived from the risk appetite of the organization and key stakeholders. They are usually recorded in the risk management plan and feed into the probability and impact matrix, whose cells show which risks lie above the threshold.

Equivalents in other frameworks

Concept Threshold at which a risk triggers action · three frameworks reviewed

Equivalents of Risk threshold in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Risk toleranceclosely relatedrefers to the measurable limit above which action is taken, and is defined more narrowly
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Risk threshold

Distinction

The term is closely related to risk tolerance in ISO 21506, which likewise describes a limit on acceptable risk exposure; the naming and perspective differ. Risk appetite is the underlying stance, and the risk threshold its measurable form. A variance threshold in project control concerns deviations that have already occurred, not risks.

In practice

For a product development project, senior management accepts no more than four weeks' delay in market entry and a five per cent budget overrun. The project manager enters these values as risk thresholds in the risk management plan. Any risk that, alone or together with others, could exceed one of these limits receives an active response.

Frequently asked questions

Does a risk threshold apply to the whole project or to individual risks?

Both are possible. Thresholds can apply to the whole project per objective and be broken down for rating individual risks.

Who sets the risk threshold?

It is derived from the risk appetite of the organization and key stakeholders and agreed with the sponsor. The project manager documents it in the risk management plan.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk threshold. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-threshold/

Short form

Risk threshold (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-threshold/ (retrieved 24 November 2026)

BibTeX
@misc{riskthreshold,
  title   = {Risk threshold},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-threshold/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-threshold/">
  <p>Measurable level of risk exposure above which a risk is addressed and below which it may be accepted.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-threshold/">Risk threshold</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.