Project Initiation Documentation
abbr. PID
Definition
In PRINCE2, the project initiation documentation (PID) is the set of management products produced during initiation that define what will be delivered in the project, why, when, by whom and how. It includes in particular the detailed business case, the project plan, the management approaches for areas such as quality, risk, issues and communication, the project management team structure with role descriptions, and the arrangements for tailoring PRINCE2 to the project. By approving it, the project board authorizes the project. It then serves as the reference basis and is updated at stage boundaries.
Equivalents in other frameworks
Concept Comprehensive project management plan · five frameworks reviewed · one false friend
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Project plan | false friendno overlap | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| ISO 21506 | Project management plan no entry yet | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| ISO 21506 | Project plan | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PMI / PMBOK | Project management plan | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PM² | Project Handbook | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project Initiation Documentation
- Topic area
- Planning and project structure
Distinction
The PMI project management plan and the project management plan under ISO 21506 serve a similar purpose. However, the PID is not a single file but a collection, and with the business case it also contains the justification. The project plan is only one component of the PID. It is also close to the project handbook in PM².
In practice
For merging two data centres, the project manager prepares the PID over six weeks. It consists of a wiki space with the business case, the project plan, four management approaches, an organization chart with role descriptions and a page on tailoring the method. The project board reviews the content in one meeting, requires a higher risk reserve and authorizes the project after the change.
Frequently asked questions
Does the PID have to be a single document?
No. It can consist of several documents, a wiki or a tool. What matters is that it is clear which content belongs to it and which version is valid.
How does the PID relate to the project brief?
The project brief is the basis for the decision to start initiation. The PID builds on it and is the basis for the decision to deliver the project.
Source and context
- Reference
- PRINCE2 7, Managementprodukte
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project Initiation Documentation. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-initiation-documentation/
Hain, D. (n.d.): Project Initiation Documentation. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/project-initiation-documentation/ (retrieved 24 November 2026)
@misc{projectinitiationdocumentation,
author = {Hain, Dennis},
title = {Project Initiation Documentation},
note = {PMDecoder, PRINCE2 7, Managementprodukte},
url = {https://pmdecoder.com/en/glossary/project-initiation-documentation/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-initiation-documentation/"> <p>Set of PRINCE2 management products defining the project; the project board authorizes the project by approving it.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-initiation-documentation/">Project Initiation Documentation</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer> </blockquote>
Found a mistake? Let us know, we check every report.