Risk Register
Definition
In PRINCE2 the Risk Register is the record in which a project’s risks are kept. It is created during project initiation and maintained continuously until the project closes. Each entry describes a risk, ideally in terms of cause, event and effect, records assessments of probability, impact and proximity, and states the chosen response, the person responsible and the current status. PRINCE2 explicitly treats risk in both directions: opportunities belong in the register alongside threats. How the register is structured, who may make entries and how often it is reviewed is set out in the risk management approach agreed during initiation. For the Project Manager the register is the basis for summarizing the risk situation in reports to the directing level.
Equivalents in other frameworks
Concept Central list of project risks · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Risk register | equivalent | — |
| general | Risk register | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Risk Register
- Topic area
- Risks and opportunities
Distinction
In content the Risk Register corresponds to the generic risk register and to the PMI Risk Register. What is specific to PRINCE2 is its firm place among the management products: the register is kept separate from open issues, which are recorded in the Issue Register. A risk is an uncertain event that has not yet occurred; once it occurs it becomes an issue and is handled through the Issue Register.
In practice
When a new point-of-sale system is introduced in 40 branches, the project manager records during initiation the risk that the supplier will deliver the interface to the merchandise management system late. She assesses probability and impact, defines an early interface test as the response and names the IT architect as owner. She also records the opportunity to terminate maintenance contracts for old devices early as part of the changeover. Before each report to the Project Board she checks which entries have changed.
Frequently asked questions
Who maintains the Risk Register in PRINCE2?
The Project Manager is responsible. Upkeep can be delegated to project support. Individual risks are given their own owners, who monitor their risk and trigger the agreed response.
Do opportunities belong in the Risk Register?
Yes. PRINCE2 understands risk as uncertainty with a possible negative or positive effect on objectives. Opportunities are therefore assessed in the same register and given their own responses, such as exploiting or enhancing them.
Source and context
- Reference
- PRINCE2 7, Praktik Risiko
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Risk Register. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-register-prince2/
Hain, D. (n.d.): Risk Register. PMDecoder, entry on PRINCE2 7, Praktik Risiko. https://pmdecoder.com/en/glossary/risk-register-prince2/ (retrieved 24 November 2026)
@misc{riskregisterprince2,
author = {Hain, Dennis},
title = {Risk Register},
note = {PMDecoder, PRINCE2 7, Praktik Risiko},
url = {https://pmdecoder.com/en/glossary/risk-register-prince2/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-register-prince2/"> <p>PRINCE2 management product that records all identified threats and opportunities of a project with assessment, responses, owners and status.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-register-prince2/">Risk Register</a>, PMDecoder, PRINCE2 7, Praktik Risiko</footer> </blockquote>
Found a mistake? Let us know, we check every report.