Change control

also: Integrated change control, Project change management

Definition

Change control ensures that changes in a project happen deliberately rather than by chance. A typical sequence comprises recording the change request, assessing its impact on schedule, costs, quality and risks, a decision by an authorized body, adjusting plans and contracts, and informing everyone affected. Every step is documented.

Equivalents in other frameworks

Concept Controlled handling of changes · three frameworks reviewed

Equivalents of Change control in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKChange controlclosely relatedemphasizes the review of and decision on change requests, less their implementation
PRINCE2Issues practiceclosely relatedCovers not only change requests but also deviations from specification, problems and concerns.
PRINCE2Issue Management Approachpartially overlappingDocument setting out the rules for issues and changes in one project, not the activity itself.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Change control

Distinction

The change request is the individual document; change control is the procedure in which it is handled. Configuration management manages versions and components of a result and complements it. Change management in the sense of organizational development, by contrast, means guiding people through change. Claims management (Nachtragsmanagement) deals with the contractual and financial side of changes between client and contractor.

In practice

During the construction phase of a municipal swimming pool modernization, change requests arrive almost every week, from an additional children's pool to different tile colours. The project manager introduces a simple form and a log. She decides small changes without cost or schedule impact herself; everything else she presents once a month to the building committee together with a cost estimate. The number of requests drops noticeably as soon as every change has a visible price.

Frequently asked questions

Who decides on changes?

The procedure defines this. There are often tiers: the project manager decides small changes, the sponsor or a change control board larger ones.

Does every project need formal change control?

Every project needs an agreed way of handling changes. How formal it is depends on size, type of contract and risk.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Change control. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/change-control/

Short form

Hain, D. (n.d.): Change control. PMDecoder. https://pmdecoder.com/en/glossary/change-control/ (retrieved 24 November 2026)

BibTeX
@misc{changecontrol,
  author  = {Hain, Dennis},
  title   = {Change control},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/change-control/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/change-control/">
  <p>Defined procedure by which changes to scope, schedule, costs or results are recorded, assessed, decided on and implemented</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/change-control/">Change control</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.