Scheduling flexibility relative to successors

Concept · 2 of 10 frameworks name this concept

The amount of time by which an activity can be delayed without pushing back the earliest start of any of its immediate successors in the schedule.

ConceptScheduling flexibility relative to successorsTopic area Network planning
Preferred term
cross-frameworkFree floatalso Free slack
equivalent
PMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Free float
Concordance of the concept “Scheduling flexibility relative to successors”. The preferred term is the designation under which the glossary lists the concept.

All frameworks at a glance

2 designations · 2 without counterpart · 6 not yet reviewed
  • PMI / PMBOK
    Free floatequivalent
  • general
    Free floatPreferred term
  • Scrum
    no designation
  • Kanban
    no designation
  • ISO 21506
    not yet reviewed
  • PRINCE2
    not yet reviewed
  • IPMA
    not yet reviewed
  • PM²
    not yet reviewed
  • Lean
    not yet reviewed
  • Six Sigma
    not yet reviewed