Critical chain method

also: Critical chain project management · abbr. CCPM

Definition

The critical chain method goes back to Eliyahu M. Goldratt, who derived it from his theory of constraints in the late 1990s. Activities are planned with tight but realistic durations without built-in safety margins. Some of the reserves removed in this way are placed at the end as a project buffer and inserted as feeding buffers where side chains join the critical chain. Control is based on the consumption of these buffers in relation to progress.

Equivalents in other frameworks

Concept Scheduling with aggregated buffers · three frameworks reviewed

Equivalents of Critical chain method in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKCritical chain methodequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Critical chain method

Distinction

The critical path method determines the longest path without regard to resources; the critical chain is the longest path taking resource conflicts into account. Unlike conventional float, which results from the calculation, the buffers here are deliberately set and managed jointly. The method regards multitasking as a major cause of delays that should be avoided.

In practice

A manufacturer of measuring instruments switches its development projects to critical chain. Instead of giving each work package a safety allowance, the teams estimate the duration that is sufficient in about half of all cases, and the project management places a shared project buffer at the end. A traffic light shows how much buffer has been consumed relative to progress. The teams also work on only one task at a time, and lead times fall noticeably in the first year.

Frequently asked questions

Why should safety margins be removed from the activities?

Because experience shows that hidden reserves get used up whether they are needed or not, for example because work is put off until the last moment. A shared buffer is easier to control.

What is a fever chart?

A chart that compares buffer consumption with project progress and is divided into green, yellow and red zones.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Critical chain method. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/critical-chain-method/

Short form

Hain, D. (n.d.): Critical chain method. PMDecoder. https://pmdecoder.com/en/glossary/critical-chain-method/ (retrieved 24 November 2026)

BibTeX
@misc{criticalchainmethod,
  author  = {Hain, Dennis},
  title   = {Critical chain method},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/critical-chain-method/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/critical-chain-method/">
  <p>Planning method that takes resource bottlenecks into account and pools the safety margins of individual activities in shared buffers</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/critical-chain-method/">Critical chain method</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.