Schedule variance

abbr. SV

Definition

Schedule variance measures how far a project is behind or ahead in budget terms. It is calculated as earned value minus planned value. A negative value shows that less work has been performed than planned by the reporting date, a positive value that the project is ahead. Because it is expressed in euros rather than days, it can be added up across all work packages.

Equivalents in other frameworks

Concept Difference between earned value and planned value · three frameworks reviewed

Equivalents of Schedule variance in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKSchedule varianceequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Schedule variance

Distinction

Cost variance compares work performed with costs, schedule variance compares work performed with the plan. It does not say whether critical activities are affected; a delay in work with float may leave the end date untouched, which only the network analysis reveals. Towards the end of the project, schedule variance inevitably approaches zero, because eventually all the planned work is performed, even if late.

In practice

A service provider equips 40 branch offices of a public authority with new technology, each with a budget of 25,000 euros. After three months, 16 sites should have been completed; 12 have been. The planned value is 400,000 euros, the earned value 300,000 euros, so the schedule variance is minus 100,000 euros. This corresponds to four sites or, at the planned pace, a good three weeks' delay.

Frequently asked questions

Why is schedule variance given in money?

Because it is calculated from budget values. This makes it comparable with cost variance; statements in days additionally require the schedule.

What is earned schedule?

An extension that expresses schedule variance in units of time and avoids the distortion towards the end of the project.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Schedule variance. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/schedule-variance/

Short form

Hain, D. (n.d.): Schedule variance. PMDecoder. https://pmdecoder.com/en/glossary/schedule-variance/ (retrieved 24 November 2026)

BibTeX
@misc{schedulevariance,
  author  = {Hain, Dennis},
  title   = {Schedule variance},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/schedule-variance/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/schedule-variance/">
  <p>Difference between the value of the work performed and the value of the work planned; a negative figure means the project is behind plan</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/schedule-variance/">Schedule variance</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.