Risk Management Approach
Definition
The risk management approach describes how a PRINCE2 project puts the risk practice into effect. It sets out the procedure by which risks are identified, assessed and addressed, and specifies the tools used, such as scales for probability and impact or a risk matrix. It records how the organization’s risk appetite is translated into tolerances, who takes on which roles in risk management, when risks are reviewed and how they are reported. It often refers to risk policies of the organization or of a higher-level programme. The approach is created during initiation and becomes part of the project initiation documentation.
Equivalents in other frameworks
Concept Arrangements for risk management in a project · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Risk management plan | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| general | Risk management plan | closely related | Same purpose; additionally translates the organization’s risk appetite into tolerances for the project board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Risk Management Approach
- Topic area
- Risks and opportunities
Distinction
The risk management plan in general usage and the PMI risk management plan serve the same purpose. The difference lies mainly in how it is embedded in the PRINCE2 management products. The approach should not be confused with the register that contains the individual risks.
In practice
For the construction of a data centre, the risk management approach defines a five-point scale for probability and impact. Risks with a product of 15 or more are reported to the project board immediately, all others in the regular report. A risk review with the team managers takes place once a month. The approach also refers to the group’s insurance policy.
Frequently asked questions
When is the risk management approach created?
During initiation, before the project is authorized for delivery. Risks noticed earlier are first recorded informally.
How does it relate to risk appetite?
Risk appetite describes how much risk the organization is willing to take. The approach translates this into specific limits above which the project board is involved.
Source and context
- Reference
- PRINCE2 7, Praktik Risiko
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Risk Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-management-approach/
Hain, D. (n.d.): Risk Management Approach. PMDecoder, entry on PRINCE2 7, Praktik Risiko. https://pmdecoder.com/en/glossary/risk-management-approach/ (retrieved 24 November 2026)
@misc{riskmanagementapproach,
author = {Hain, Dennis},
title = {Risk Management Approach},
note = {PMDecoder, PRINCE2 7, Praktik Risiko},
url = {https://pmdecoder.com/en/glossary/risk-management-approach/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-management-approach/"> <p>PRINCE2 management product defining how risks in the project are identified, assessed, controlled and reported.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-management-approach/">Risk Management Approach</a>, PMDecoder, PRINCE2 7, Praktik Risiko</footer> </blockquote>
Found a mistake? Let us know, we check every report.