Highlight Report
Definition
In PRINCE2 the Highlight Report is the Project Manager’s regular status report to the Project Board. It enables the Board to direct the project by exception: as long as the reports show that the stage is running within its tolerances, the Board need not intervene or hold meetings. The report summarizes what was achieved in the reporting period, what is planned for the next period, how time, cost, scope and quality stand against the tolerances, which significant issues and risks exist, and which changes have been approved or proposed. Frequency, format and distribution are set during initiation and in the stage plans. Further recipients, such as stakeholders outside the Board, are possible.
Equivalents in other frameworks
Concept Regular project status report · two frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Progress report | closely related | Report from the Project Manager to the Project Board per management stage, geared to management by exception. |
| PM² | Project Progress Report | closely related | defined PM² artefact from the Project Manager to the Project Steering Committee |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Highlight Report
- Topic area
- Stakeholders and communication
Distinction
The Highlight Report corresponds to the progress report in ISO 21506 and the PM² Project Progress Report, but is explicitly geared to direction by the Project Board under management by exception. The Checkpoint Report reports one level lower, from the team to the Project Manager. If a tolerance breach is forecast, the Highlight Report is not enough; an Exception Report follows.
In practice
In a project to renew the network equipment at twelve school sites, the Project Board receives a Highlight Report every two weeks. The latest report states that eight sites have been switched over, costs are on plan and the schedule is five days behind target but still within tolerance. It lists supply shortages for switches as a risk. The Board takes note of the report without calling a meeting.
Frequently asked questions
How often is a Highlight Report produced?
At the intervals set by the Project Board, often every one to four weeks. The frequency can differ from stage to stage and depends on the risk and pace of the project.
Does the Highlight Report replace Project Board meetings?
Largely, yes. PRINCE2 intends the Board to be kept informed through reports and to meet only at fixed decision points or in exception situations. Informal conversations are not affected.
Source and context
- Reference
- PRINCE2 7, Praktik Fortschritt
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Highlight Report. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/highlight-report/
Hain, D. (n.d.): Highlight Report. PMDecoder, entry on PRINCE2 7, Praktik Fortschritt. https://pmdecoder.com/en/glossary/highlight-report/ (retrieved 24 November 2026)
@misc{highlightreport,
author = {Hain, Dennis},
title = {Highlight Report},
note = {PMDecoder, PRINCE2 7, Praktik Fortschritt},
url = {https://pmdecoder.com/en/glossary/highlight-report/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/highlight-report/"> <p>Regular PRINCE2 report from the Project Manager to the Project Board on the status of the current management stage and the project.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/highlight-report/">Highlight Report</a>, PMDecoder, PRINCE2 7, Praktik Fortschritt</footer> </blockquote>
Found a mistake? Let us know, we check every report.